What the attachment card is and when it is created
A permit with PSZN may carry a separate one-page attachment card for each especially dangerous work. If the service requires two such works, for example work at height on the drive system and work on the machine's electrical installation, two cards are created, each on its own page. The printout is one PDF or a separate attachment, depending on how the plant circulates documents.
In InnerWeb especially dangerous work is a separate object attached to the permit and passes through a state machine with eight states. The card is therefore a record of this object on paper or in PDF, not a separate document filled in outside the system.
Step by step: from request to printout
The following order works well in plants that want the card to be ready before the service technician arrives on the hall.
- Step 1. The plant coordinator opens the service permit for the selected machine and location.
- Step 2. The especially dangerous work arising from the scope of the service is attached to the permit.
- Step 3. Risks from the location and work-type catalogue attach automatically, and the ordering person adds ad hoc ones.
- Step 4. A user on the plant side approves or rejects the PSZN. The external company cannot do this.
- Step 5. The system generates the attachment card for each PSZN and links it with the permit printout.
- Step 6. The plant prints one PDF or a single attachment and hands it to the service technician or posts it by the machine.
Risk sections on the permit printout
Who approves the card
Only a user on the plant side, not the external company, may approve or reject the PSZN. In practice this is assigned to the OHS manager or a person authorised in the plant's procedure. It is good to name a deputy in the role configuration, because approval should not wait for one person who happens to be on leave.
The status of the PSZN is independent of the permit status. Open PSZN tasks do not block the permit from moving from preparation to the main work, or from the main work to closing. This means that before accepting the machine the OHS manager checks the permit status and the status of each card separately.
Combining the card with the printout in the plant's format
The print template of the permit can reproduce the plant's paper form through an uploaded template matrix. A plant that has used its own form for years does not have to retrain team leaders and controllers to a new layout. The attachment card is added to this template as a further page.
The risks on the printout are arranged in five sections with deduplication: common risks, location hierarchy, additional locations, type of dangerous work and user risks. Thanks to deduplication the card fits on one page, even when the service concerns a machine with an extensive risk catalogue.
One PDF or a single attachment
One PDF is convenient when the plant archives the permit as a whole. A single attachment is convenient when the card goes to a different recipient than the permit, for example to the person supervising the zone. The choice belongs to the plant.
Most common pitfalls
The first pitfall is assuming that an approved permit means an approved PSZN. These are two statuses. The second is expecting the card to appear without risks being assigned to the location: if the catalogue for a given machine is empty, the card will be poor, and ad hoc completion will fall on the ordering person. The third is the lack of a deputy approver.
The fourth pitfall concerns closing. A PSZN cannot be closed while more than one employee remains on site, so before acceptance the plant should check whether the service technicians have left the place of work. The checklist for accepting the machine after service describes this in detail.
Video
Frequently asked questions
Does every service work require a PSZN card?
A card is created for especially dangerous works attached to the permit. Which service works count as such is set by the plant's procedure.
Can the service company approve the card?
No. Only a user on the plant side approves or rejects it.
Can the appearance of the card be adjusted?
The print template of the permit reproduces the plant's form through an uploaded template matrix, and the card is added to it as a further page.
Let us reproduce your permit form