Checklist for accepting a machine back to production after service

A machine returns to operation only when everything in the system concerning the service is closed, and production has physically checked the workstation. The checklist for the team leader and the production manager divides acceptance into two parts: what must be closed in the system, and what is assessed on site before the machine is admitted back to work.

Part one: what must be closed in the system

Acceptance starts at the screen, not on the hall floor. The team leader checks three things: whether the service permit is closed, whether each linked especially dangerous work is closed, and whether the employee list at the place of work is empty. The status of the PSZN is independent of the permit status, so a green permit is not enough to accept the machine.

An especially dangerous work will not close while more than one employee remains on site. If the PSZN stays open despite the service being finished, first check whether someone from the crew has stayed at the place of work, and only then look for the cause in the work itself.

Part two: what production checks physically

The system records statuses and time, but it cannot see the state of the workstation. Production physically checks whether the service tools and materials have been removed, whether guards and safety devices have been returned to their place, whether energy locks have been removed by the people who fitted them, and whether any foreign objects remain within the machine. This is the plant's list, which no system can replace, and the team leader records its result in the acceptance.

Why the order matters

System first, then the hall. If the team leader starts acceptance with a visual inspection and only then sees an open especially dangerous work, he loses time and has to repeat the inspection. The reverse order saves steps.

Acceptance points: system versus hall

Acceptance points: system versus hallDistribution of 11 acceptance points: four checked in the system, five physically on the hall floor and two concerning the decision.Checked in the system: 4 points (36.4%)Checked physically on the hall floor: 5 points (45.5%)Decision and record: 2 points (18.2%)11pointsChecked in the system4 points (36.4%)Checked physically on the hall floor5 points (45.5%)Decision and record2 points (18.2%)
Source: Division of the checklist points from this page

The role of location in acceptance

After a person enters the place of work the system can add the employee to the permit at that location, and after leaving it can remove them from the list. For acceptance this gives a simple test: the list of people at the place of work after the service is finished should be empty. The permit time and the working time of each employee are counted separately, so the team leader sees from when to when the work window lasted and can compare it with the entry in the machine log.

The position comes from BLE signals from beacons, without GPS, and in a building we assume roughly one beacon per 100-200 m². For very small machine positions, for example a cabin in a tight corner of the hall, the plant may add a beacon so that the outline of the work is reliable.

What to record in the acceptance and who to hand it to

After both parts the team leader records the decision: machine accepted back to operation, accepted with a reservation, or not accepted. A reservation is described specifically, for example a missing guard to be fitted within a given time, together with the person responsible. An acceptance recorded only as an empty box helps nobody at the next failure.

Production management receives information about the acceptance, and maintenance receives the reservations. Plants with a two-signature procedure record the acceptance with the signatures of both sides, and the system ensures that the service record preceding it, that is the permit, the tasks and the times, is complete.

Checklist

Video

Frequently asked questions

Will the system release the machine back to operation by itself?

No. InnerWeb is a complementary system: it records the service statuses and shows whether the service is closed. The decision to return the machine to operation belongs to production.

What if the PSZN will not close?

Check whether more than one employee remains at the place of work, because this blocks closing. Only then look for another cause.

Does a closed permit mean the machine is safe?

No. It means the service process has been closed in the system. The safety of the workstation is confirmed by the inspection by production.