Templates and the course of the permit
The first check concerns the templates. The course of a permit, that is the preparatory, main and closing tasks and the automatic closing, follows the template linked to the location. Templates are configured in the installation data, without changes to the code, so the security manager can agree their content with the maintenance department before the start.
Check that the welding shop and its zones have the right templates assigned, and that the tasks match the actual order of work. A template that does not match practice is the most common reason why issuers work around the system in the very first week.
Risks assigned to locations
The second check concerns risks. They are assigned with the required protective measures to locations at every level of the hierarchy: hall, area, line, place, and to the high-risk work type. For the welding shop this means the assignment should cover both the welding shop itself and the workstations within it.
Pay attention to the hot work type, which in the system is one type with several possible subtypes. The issuer selects the type and subtypes, and risks assigned to the type appear on the printout. A missing risk on the list means a missing protective measure on the printout, so gaps should be filled in the risk editor before the start.
Hours after hot work ends until closing
Authorisations, approval and fire watch
High-risk work requires a knowledge check, approval by a user on the plant side and, for hot work, a fire watch period after the work ends. Only a user on the plant side can approve or reject a PSZN, so before the start decide which workers hold this role and who replaces them on other shifts.
Fire watch after hot work is carried out by a worker of the external company. The path is a 1-hour stage, then a 4-hour stage, and moving to the 4-hour stage is possible only one hour after the watch has started. Closing is blocked until at least 3 hours of watch have passed. If the work ends at 14:00, the earliest closing therefore falls at 17:00, which should be taken into account in the shift plan.
Closing rules and the independence of statuses
A PSZN cannot be closed while more than one worker remains on site. This is a rule to discuss with the external companies before the start, so that a team does not leave the workstation in a hurry before the end of the shift.
Open PSZN tasks do not block the move of the permit from preparation to the main works or to completion, so the permit status does not replace the PSZN check. Open tasks move to the main works, where the contractor or the administrator confirms them. Decide who checks both statuses at the end of the day.
Checklist
Video
Frequently asked questions
Can a plant employee carry out the fire watch?
According to the feature documentation, the fire watch after hot work is carried out by a worker of the external company. Approval of the work remains on the plant side.
Can the template be changed after the start?
Templates are configured in the installation data, without changes to the code. Changes should, however, be agreed before the first week.
What if the work ends just before the end of the shift?
Closing is possible only after at least 3 hours of fire watch, so the shift plan should take this into account.