Why the watch is a separate stage
Particularly hazardous work with fire requires, in addition to a check of competence and approval by a user on the plant side, a watch period after the work ends. It is a separate stage, because an ignition source can reveal itself after some time, when the contractor is already thinking about the next job.
Without a fixed watch window, the decision to close the permit depends on who is on shift and how much they are in a hurry. Good practice is to let a rule written into the system decide the time, not a person.
The watch path in InnerWeb
For hot work the watch path applies: a 1-hour stage, then a 4-hour stage, and closing is blocked until at least 3 hours of watch have elapsed. The watch is carried out by an employee of the external contractor, and moving to the 4-hour stage is possible only one hour after the watch starts.
This arrangement has a practical consequence. The shift manager does not plan to close the permit right after welding. They plan it with a margin of at least 3 hours and include this in the shift schedule.
- Stage 1: the first hour after the hot work ends.
- Stage 4: the extended watch, available after one hour from the start.
- Lock: closing impossible before at least 3 hours have elapsed.
Watch timeline after welding that ends at 1:00 p.m.
Seven good practices for the shift manager
The practices concern work in the welding bay, next to the paint shop and in the assembly hall, where welding is carried out by the plant's own employees and by external contractors.
Appoint the watch keeper before the work starts
The watch belongs to an employee of the external contractor. If the contractor does not name the person before the start, the watch begins with a search for someone who has the time. Enter the watch keeper in the permit team at the preparation stage.
Plan the closing with a margin
A minimum of 3 hours of watch means that work finishing 30 minutes before the end of the shift will not close in the same shift. Plan the handover of the watch to the next shift, or start the welding earlier.
Do not skip ahead to the 4-hour stage
Moving to the 4-hour stage is possible only one hour after the watch starts. The manager cannot shorten this period, so it is worth writing into the procedure that the 4-hour stage is the standard for work near flammable materials.
Check how many people are on site
A PSZN cannot be closed while more than one person remains on site. Before closing, make sure the team has left the place and at most the watch keeper remains.
Separate the watch from the approval
The approval is given by a user on the plant side, and the watch is kept by an employee of the external contractor. Do not combine these roles in one person just because it is convenient.
Do not tie the watch to the status of the whole permit
The PSZN and the permit status are independent, so an unclosed watch does not block the permit from moving to completion. Control the closing of the watch separately, on the PSZN task list.
Record the type and subtypes of the work
One PSZN can have one type and several subtypes, for example hot work with several subtypes at once. A well-described subtype makes later analysis of incidents easier.
An example of a shift layout: an illustrative calculation
For example, welding ends at 1:00 p.m. Stage 1 runs until 2:00 p.m., the minimum time before closing elapses at 4:00 p.m., and the 4-hour stage ends at 5:00 p.m. If the shift ends at 2:00 p.m., the watch must pass to the second shift, or the closing moves to the following day.
This is an illustrative example based on an assumed end time of the work. At a specific plant the schedule depends on the organisation of shifts and on the watch keeper appointed by the contractor.
Checklist
Video
Frequently asked questions
Can the watch be shortened if nothing happens?
No. Closing is blocked until at least 3 hours of watch have elapsed, regardless of how the situation looks.
Who carries out the watch?
An employee of the external contractor. The approval, however, is given by a user on the plant side.
When can the 4-hour stage be reached?
Only one hour after the watch starts. Before that the system does not allow it.