Does an open PSZN block the permit?
No, it does not. In InnerWeb the permit and the high-risk work (PSZN) have separate statuses, and open PSZN tasks do not hold back the permit from moving from preparation to the main works or to completion. This is a deliberate business decision, documented in the feature description: the system does not chain the two life cycles into one dependency.
For the coordinator this changes the perspective. The permit status tells you which phase the whole work assigned to the external company is in. The PSZN status tells you whether specific risky activities, for example welding or cutting in a machine plant, have been approved and closed. One does not replace the other, so checking both statuses belongs to the person responsible for the work area.
What happens to open PSZN tasks when the permit starts?
When the permit starts, open PSZN tasks move out of the preparation phase into the main works. There the contractor or the administrator confirms them. A task does not disappear and is not automatically accepted; it only changes its place in the permit flow.
In practice the shift supervisor should treat the start of the permit as a checkpoint, not as proof that everything is closed. A good habit is to review the list of open PSZN tasks right before the main works begin and agree who in the contractor team confirms them first.
Fire watch after hot work in hours
Who approves and who confirms PSZN?
Only a user on the plant side can approve or reject a PSZN. The external contractor cannot do this, even if they lead the whole team. The separation of roles is intentional: the assessment of whether the work may take place belongs to the host of the site, not to the company that performs it.
Confirming tasks during the main works is a separate activity. It is carried out by the contractor or the administrator. That is why procedures should distinguish two terms: approval (the plant's decision to admit the work) and confirmation (recording that a task has been done during the work).
- Approves or rejects: a user on the plant side.
- Confirms tasks in the main works: the contractor or the administrator.
- Performs fire watch after hot work: a worker of the external company.
When can PSZN not be closed?
A PSZN cannot be closed while more than one worker remains on site. The rule prevents a situation in which the formal closing comes before the team actually leaves the work area. It is enforced by a state machine with eight states, in which PSZN is a separate object attached to the parent permit.
For hot work an additional fire watch path applies: a 1-hour stage, then a 4-hour stage, and closing is blocked until at least 3 hours of watch have passed. The fire watch is carried out by a worker of the external company, and moving to the 4-hour stage is possible only one hour after the watch has started. We cover how to plan the fire watch window in the hall in a separate article.
How many types and subtypes can one PSZN have?
One PSZN can have one type and several subtypes. For example, the hot work type can appear together with several subtypes at the same time, which matches the reality of a workshop where cutting, grinding and welding are combined at one workstation.
The work type also organises what the system shows the person issuing the permit. Risks with the required protective measures can be assigned to the high-risk work type, so the choice of type brings up the right set of hazards on the permit printout. The assignment of risks to locations is covered in our article on risks assigned to hall locations.
Video
Frequently asked questions
Can an administrator confirm a PSZN task on behalf of the contractor?
Yes. In the main works the task is confirmed by the contractor or the administrator. Approval of the work itself stays with the user on the plant side.
Does closing the permit also close the PSZN?
No. The statuses are independent, so closing one does not settle the other. The shift supervisor should check both statuses before the end of the working day.
Can a plant employee carry out the fire watch?
According to the feature documentation, the fire watch after hot work is carried out by a worker of the external company. Approval of the work remains on the plant side.
How does the system know someone is still on site?
Closing is blocked while more than one worker remains on site. How a location links a worker to a permit is covered in our FAQ on joining a permit by location.