Why can battery power be a condition for access to the site?
In continuous-operation plants every intervention in the electrical installation requires permits, planned shutdowns and often work in hazardous zones. Battery power eliminates most of these steps: the transmitter is mounted with a cable tie or adhesive, with no cables and no mains supply.
Beacons are usually placed about every 100 m along plant roads, on poles and structures. With cabling, each such point would require a cable route, protection and acceptance.
What does the example of a 100-transmitter network on 8 floors show?
Battery power made it possible to install a network of 100 transmitters on 8 floors in 2 days on site, without switching off the installation and without connecting to a power supply. This is a fact from a real deployment and a reference point for your own estimates.
This means about 50 transmitters per day per crew. In the cabled variant the pace depends on the length of the routes, the difficulty of the passages and the availability of shutdowns, so it cannot be determined without surveying the facility.
Cumulative maintenance cost of one battery transmitter
How do you compare the cost over a 4-year horizon?
The battery variant costs indicatively PLN 7 net per unit per month to maintain, which is PLN 84 per year and PLN 336 over 4 years. This covers battery replacement, monitoring and support. The mains-powered variant has no battery fee, but has a connection cost for every point.
The break-even point is simple: if the full cost of connecting one point to the network, meaning cable, protection, labour, shutdowns and acceptance, exceeds PLN 336, the battery variant is cheaper over 4 years. You enter the value of K for your facility yourself, after surveying the routes.
It is worth adding the cost of downtime or of a service window if cabling requires stopping part of the installation. This item often outweighs the price of the cable itself.
When does mains power make sense?
Mains power is justified where a supply point already exists at the mounting location, for example at lighting fixtures, or when the period of use is much longer than 4 years. In that case the weight of the battery's recurring cost grows compared with a one-off connection.
In hazardous zones there is a requirement for explosion protection of the supply installation as well. The InnerWeb beacon has ATEX certification for zones 2 and 22 and does not need a mains supply, which simplifies the documentation.
What risks do both options carry?
In the battery variant the risk is battery wear, which the maintenance service limits through monitoring and planned replacement. Battery life is not given as a guarantee, so the budget rests on the monthly rate, not on a promise of a number of years.
In the mains-powered variant the risks are a failure of the point's power supply, damage to a cable during construction work and the need to shut down the installation for every repair.
- Battery: planned replacement within the service, no intervention in the installation.
- Mains: connection cost and service windows, dependence on the power supply.
- Both: coverage calibration before the alarms are switched on.
How do you prepare the comparison for a management decision?
Prepare a table with four rows: initial cost, maintenance cost over 4 years, installation time and the risk of downtime. For the battery variant enter PLN 336 per point in maintenance and the installation time from the survey; for the mains variant enter your own K and the time from the contractor's offer.
Present the results as a range, not as a single figure, because both variants depend on the facility. Such a document supports the decision and serves as evidence of proper analysis in a procurement audit.
Break-even point of battery power over 4 years
| Parameter | Value |
|---|---|
| Battery variant maintenance rate | 7 PLN net per unit per month |
| Horizon | 48 months |
| Break-even connection cost per point (K) | 336 PLN net per point; above this threshold the battery variant is cheaper |
Result: 7 x 48 = PLN 336 net per point; the battery variant is cheaper when K exceeds PLN 336
Note: Example calculation. Indicative ranges from deployments in 2025 and 2026; price quoted individually. The actual connection cost K depends on the facility.
Video
Frequently asked questions
Are battery transmitters cheaper than mains-powered ones?
It depends on the connection cost per point. If cable, protection, labour and shutdowns cost more than PLN 336 per point, the battery variant wins over a 4-year horizon.
How long does it take to install battery transmitters?
In one deployment a network of 100 transmitters on 8 floors was installed on site in 2 days, without switching off the installation.
Do battery transmitters need a power supply in an Ex zone?
No. The InnerWeb beacon has ATEX certification for zones 2 and 22 and does not need a mains supply.
What about battery replacement?
It is part of the maintenance service, alongside monitoring of correct operation and ongoing support.