How many transmitters per hall: a practical guide

The designer receives the plant layout and has to work out how many transmitters to order. The recommended density is 1 transmitter per 100 to 200 m2 in a building and roughly every 100 m on plant roads. Below we show how to apply these rules to a hall from scratch, how to account for obstacles and how to confirm the result with coverage calibration.

Where should the count of transmitters start?

Start from the plant layout with dimensions and divide it into zones: halls, rooms, plant roads, yards and difficult places such as tanks or gantries. Each zone follows a different placement rule, so counting for the whole plant with one number gives a wrong result.

A person's position results from the signals of several transmitters averaged on the map, not from the strongest one. That is why the count is not the only thing that matters: even coverage matters too, so that at every place the phone can hear several transmitters at once.

How do you convert the floor area of a hall into transmitters?

In a building the recommended density is 1 transmitter per 100 to 200 m2. The lower bound, 100 m2 per transmitter, gives a denser network and higher accuracy, while the upper bound of 200 m2 limits the cost where an indicative location is sufficient.

Formula: the area divided by 200 gives the minimum number, and the area divided by 100 gives the recommended number for greater accuracy. For a 5,000 m2 hall this gives 25 and 50 transmitters respectively.

  • 2,000 m2: from 10 to 20 transmitters.
  • 5,000 m2: from 25 to 50 transmitters.
  • 10,000 m2: from 50 to 100 transmitters.

Number of transmitters for halls of different floor areas

Number of transmitters for halls of different floor areasBar chart: for 2,000, 5,000 and 10,000 m2 respectively 10 to 20, 25 to 50 and 50 to 100 transmitters020406080100units1 per 200 m2 (minimum) (2,000 m2): 10 units10 units1 per 100 m2 (recommended for accuracy) (2,000 m2): 20 units20 units2,000 m21 per 200 m2 (minimum) (5,000 m2): 25 units25 units1 per 100 m2 (recommended for accuracy) (5,000 m2): 50 units50 units5,000 m21 per 200 m2 (minimum) (10,000 m2): 50 units50 units1 per 100 m2 (recommended for accuracy) (10,000 m2): 100 units100 units10,000 m2
  • 1 per 200 m2 (minimum)
  • 1 per 100 m2 (recommended for accuracy)
Source: Example calculation at a density of 1 transmitter per 100 to 200 m2 (InnerWeb reference data)

How do you count plant roads and yards?

On plant roads transmitters are placed roughly every 100 m. For a 1 km section this means about 10 points, plus points at junctions and bends where the position must be unambiguous.

In large plants the spacing is matched to the road layout: in a network of 600 beacons on road routes, the spacing was matched to the roads and installation was priced per unit including mounting. For storage yards the calculation uses a grid instead of a line, taking into account racks and containers.

ATEX transmitters for zones 2 and 22 are mounted on poles and structures with cable ties or adhesive, without cables.

How do you account for obstacles and difficult places?

Metal structures, racks and tank walls attenuate the signal, so in such places points are densified or transmitters are mounted inside the area. Location accuracy depends on transmitter coverage, including halls, tanks and gantries.

Alarm and SOS do not work outside network coverage without a separate coverage solution. If the facility has shadow zones, plan them at the design stage, not after the first incident.

How do you confirm the calculation result on site?

Network coverage is calibrated at the start of the deployment, before the alarms are switched on. Calibration shows whether the position is stable at every place and allows points to be added where the result deviates from expectations.

During calibration the transmission power is also fine-tuned to the hall. This reduces interference and, as a result, extends battery life. It is worth recording the calibration results and attaching them to the acceptance documentation.

How do you estimate the cost once the transmitters are counted?

Once the number of points is set, multiply it by the indicative maintenance rate of PLN 7 net per unit per month and by the number of months. For 50 transmitters and 48 months this gives PLN 16,800 net. These are indicative ranges from deployments in 2025 and 2026, and the price is quoted individually.

If the hall has several zones with different densities, add up the results for the zones and add a 10 percent reserve in the budget calculation for points added after calibration. This is an example assumption, not a rule.

Example calculation

Number of transmitters for a 5,000 m2 hall

Assumptions
ParameterValue
Floor area of the hall5000 m2
Minimum density200 m2 per transmitter
Recommended density for accuracy100 m2 per transmitter

Result: 5,000 / 200 = 25 transmitters (minimum), 5,000 / 100 = 50 transmitters (recommended)

Note: Example calculation. The final number is confirmed by coverage calibration at the facility.

Video

Frequently asked questions

How many transmitters does a 5,000 m2 hall need?

From 25 to 50 units at a density of 1 transmitter per 100 to 200 m2. The exact result is confirmed by coverage calibration.

How many transmitters per kilometre of plant road?

About 10, because the spacing is roughly 100 m, plus points at junctions and bends.

Does the system work without GPS?

Yes. The position results from the signals of several transmitters averaged on the map.

What about places outside network coverage?

Alarm and SOS do not work outside network coverage without a separate coverage solution, so shadow zones are planned at the design stage.