Why mounting without drilling and cables matters
ATEX radio beacons are placed about every 100 m along plant roads and mounted on poles and structures with cable ties or adhesive, without cables and without mains power. As a result, mounting does not compromise load-bearing structures, requires no electrical qualifications and can be planned as a simple mechanical task.
Battery power means installation without intervening in the electrical installation, which in continuous-operation plants is often a condition for entering the site. For steel structures there is a second argument: the absence of holes and welds does not change the structural documentation and does not require a new load-bearing assessment.
Practice 1 and 2: choosing the place and the spacing
Choose the mounting place based on the plan, not on the spot ad hoc. On plant roads assume a spacing of about 100 m, but adjust the plan at bends, junctions and narrow passages, where position matters most.
On elevated roadways and lattice structures, mount the transmitter where the maintenance team has safe access. A transmitter placed so that battery replacement requires scaffolding turns a cheap service into an expensive operation, so assess access already at the planning stage.
For orientation: a 1,000 m section of elevated roadway requires about 11 transmitters at a 100 m spacing, counting both ends. This figure is a sample calculation and serves for a preliminary quotation, not for execution design.
Transmitters on an elevated roadway section at 100 m spacing
Practice 3 and 4: the method of fixing and the surface
A cable tie works well on profiles, pipes and poles with a regular cross-section. Adhesive is used where a cable tie cannot be fitted, for example on flat sheet metal surfaces. In both cases clean the surface of dust, oil and loose paint before fixing.
Do not mount the transmitter directly against large masses of metal if the plan allows moving it a few centimetres away. Metal affects the signal range, and the position depends on the strength of the signal received from several transmitters. After mounting, check with a phone walk whether the signal is visible from both sides of the structure.
Practice 5 and 6: location in the data and uniqueness of the identifier
Every mounted transmitter must be assigned in the data to the correct location. Radio beacons located on a road but assigned in the data to a warehouse cause a route jump. A wrong position in the data is corrected once for all future routes, but it is better to enter it correctly during mounting.
Check the uniqueness of identifiers during mounting. Two physical transmitters with the same identifier placed hundreds of metres apart produce a single position in the system. Keep a simple register: identifier, place, date, person mounting, photo of the transmitter on the structure.
Practice 7: acceptance and review after the first season
After mounting, carry out a test walk along the entire route and compare the positions with the plan. Only after the discrepancies have been corrected are alarms launched. Record the result in a protocol, because it is material for later reviews and for the audit.
After the first season carry out a review: whether the fixings hold after temperature changes, vibration and precipitation, whether no transmitter has been obscured by new installations, and whether the spacing still matches traffic on the roads. Update the plan immediately with any changes to the plant layout.
Checklist
Video
Frequently asked questions
Does mounting transmitters require drilling into the structure?
No. Transmitters are fixed with cable ties or adhesive, without cables and mains power, so the load-bearing structure is not damaged.
What spacing should be assumed along plant roads?
About 100 m as a starting point. The plan is adjusted at bends, junctions and narrow passages, and after the test walk.
What happens when a transmitter is assigned to the wrong location?
The route shows a jump, because a transmitter located on a road is assigned in the data to a warehouse. The error is corrected once in the data and works for all future routes.