Starting point: a concept for a three-shift moulding plant
The scenario covers a plastics processing plant with 20 injection machines working in three shifts, carrying out about 8 mould changes a week. It is a concept and an illustrative calculation, not a description of an implementation at a specific customer. Its purpose is to show how the process would look using the system's ready-made functions.
A mould change is repetitive work, but it is not routine from the safety point of view: a crane or forklift enters the machine area, a mould weighs from several hundred kilograms to several tonnes, and water, hydraulic and electrical connections must be disconnected and reconnected. That is why the permit must be complete and, at the same time, quick to issue.
A seven-step wizard instead of a blank form
The shift supervisor opens the new permit wizard, which guides them through seven steps: basic data, particularly dangerous work, tasks, risks, team, notifications and summary. The order is fixed, so a new supervisor does not have to remember where to start.
In the particularly dangerous work step, the tiles are sorted by how often a given user selects them. A supervisor who issues mould change permits every shift sees the relevant tiles at the top and does not scroll through the whole catalogue. A form in progress is saved in the browser, so an interruption by a phone call from the hall does not mean starting again from scratch.
- Step 1: location (injection machine) and contractor company or own maintenance team
- Step 2: choice of particularly dangerous work, for example work at height or with a crane
- Step 3: tasks from the template for the location and contractor
- Step 4: risks collected automatically from the plant hierarchy
- Step 5: team with qualification checks, step 6: notification list, step 7: summary
Shift supervisors' time on permits per week
Task template: the key to saving time
The task template is selected for the location and the contractor company. For a mould change it contains the typical sequence: isolating power and hydraulic energy, closing cooling circuits, removing guards, securing the mould against movement, fitting, a test run without material and release. The supervisor does not build this list from scratch, only confirms it.
Tasks from the template can be edited only for the current permit. When a mould requires an extra step, for example removing a temperature sensor, the supervisor adds it in that single permit and can save the result as a new template if the step should return at future changes. The plant standard therefore stays under control, and deviations remain visible.
Summary with the predicted status and print preview
The last step shows the predicted permit status calculated on the server, together with a print preview from the plant matrix, before the permit is created. The supervisor sees whether the permit goes straight to work or requires approval, and can correct the data before the document reaches the contractor.
Notifications follow the list from step six: one email per person, and the person who opens the permit does not receive it, because they create it themselves. Maintenance and health and safety departments know about the planned mould change, but mailboxes do not fill up with duplicates.
Illustrative calculation: how many minutes the template saves
We assume 8 mould changes and 4 service permits a week, that is 12 permits, and a saving of 10 minutes per permit once the template is introduced. This gives 120 minutes a week, or 2 hours of shift supervisors' time, and roughly 104 hours a year over 52 weeks.
Repeatability matters more than the hours themselves: every mould change has the same set of tasks and a record in the audit trail with the author and time. The calculation is illustrative and does not replace measurement in a specific plant. It shows an order of magnitude that should be verified during the pilot of one hall.
Conclusions for the concept
The scenario shows that for repetitive work such as a mould change, a template gives more than yet another field in a form. InnerWeb is a software vendor and works as an independent system that complements the plant's existing systems, so templates are introduced without replacing machines and without interfering with injection machine controls.
Permit time in a three-shift moulding plant
| Parameter | Value |
|---|---|
| Mould changes | 8 a week |
| Service permits | 4 a week |
| Saving after introducing the template | 10 min per permit |
Result: 120 minutes a week, about 104 hours a year
Note: Illustrative calculation based on concept assumptions, to be verified during the pilot.
Video
Frequently asked questions
Can a shift supervisor issue a mould change permit on their own?
Yes, the wizard is designed for the person issuing the permit. The task template and the risks from the plant hierarchy limit their work to confirmation and, if needed, adding steps.
Can tasks from the template be changed?
Tasks are edited only for the current permit. The change can be saved as a new template if it should apply to future changes.
What happens if the supervisor is called away while filling in the permit?
A form in progress is saved in the browser, so an unfinished permit survives a page refresh.
Let us test the template in your hall
Book a conversation about a mould change permit template. We will walk through the wizard using an example of your injection machine.
Let's talk