Stage 0: choosing the hall and the group of users
The pilot covers one hall and all the shift supervisors who issue permits in it, including those on the night shift. Leaving out one shift in the pilot means that documents start to diverge in the very first week.
Also choose one service company that regularly works in this hall. Implementing with the contractor involved shows the full cycle from report to approval straight away.
Stage 1: task templates for the most common jobs
The task template is selected for the location and the contractor company. Start with the two most common jobs: mould change and hydraulic service. Prepare the templates together with the shift supervisors, not behind their backs, because they are the ones who will confirm or reject how practical they are.
For the first permits, allow editing of tasks for the current permit and saving the result as a new template. After two weeks you have a library of templates based on real work.
Proposed schedule for a one-hall pilot
Stage 2: risks in the hall, area and line hierarchy
Add risks after the templates, because only then is it clear which hazards actually come back. The print is assembled from five sections with deduplication, so the catalogue can be built gradually and improved after the first prints.
Health and safety runs the risk editor and collects the supervisors' comments. A reported missing risk is added once, and after that it can be selected by everyone.
Stage 3: qualifications and training
The qualification check when a permit is created works only once data on medicals and licences is complete. Switch it on after tidying up the HR data, so that the first messages about gaps concern real gaps, not empty fields.
A good idea is one week of working in warning mode before full enforcement. Shift supervisors get used to the messages, while HR and health and safety correct the data.
Implementation pitfalls
The most common pitfalls are templates that are too long, risks transferred in bulk from old paper forms, and the lack of one owner of the catalogue. A template with dozens of tasks to confirm discourages more than paper does, so it is better to have two shorter templates than one extensive one.
- Templates built without the participation of shift supervisors
- Too many tasks in one template
- No designated owner of the risk catalogue
- Switching on the qualification check before tidying up the data
- Leaving out the night shift from the pilot
Criteria for closing the pilot
You consider the pilot finished when all permits for mould changes and service in the hall are created in the wizard, and the print preview from the plant matrix has been accepted by health and safety. Only then do you plan the extension to other halls. InnerWeb is a software vendor and integrates with the plant's existing systems, so the extension does not require changes to machines.
Video
Frequently asked questions
Where should the pilot start?
With one hall, all shifts and the two most common jobs: mould change and hydraulic service.
Why are qualifications left until the end?
Because the check works only with complete data on medicals and licences.
Can tasks from a template be changed during the pilot?
Yes, for the current permit, with the option of saving the result as a new template.
Let us plan a pilot of one hall
Book a conversation and agree on the hall, the group of shift supervisors and the first two templates to implement.
Let's talk