Where the survey sits in the schedule
The schedule of a large location rollout starts with the contract and the site survey with propagation measurements, followed by the layout design. Then come the server and the LoRa network, then mounting and calibration zone by zone, and finally accuracy tests, training and acceptance.
The survey is therefore the first technical stage, and everything else depends on its quality. A mistake in the assumptions at this stage repeats itself in every zone.
How the site survey runs
The supplier's engineer walks the site together with a representative of the plant, measures signal propagation in representative places and records the conditions: floors, walls, metal structures, zones where work requires permits.
The measurements concern the environment in which the system will work, not laboratory conditions. For this reason difficult places are measured, such as halls with dense machinery or rooms behind thick walls.
- walk through the site with a representative of the plant
- propagation measurements in representative places
- notes on walls, floors and structures
- definition of zones with restricted access
Hall of 5,000 m2: number of transmitters under the card assumptions (sample calculation)
Where the number of beacons comes from
The exact number of beacons depends on assumptions about floors and walls, so it is calculated from zero for a given facility rather than filled up to a fixed figure. The first quote may be an estimate, but the binding number is set after the survey.
As a reference point, 1 transmitter per 100-200 m2 in a building is assumed, and a transmitter about every 100 m along plant roads. The system works without GPS: the position results from the signals of several transmitters averaged on the map.
Calculation example
For a hall with an area of 5,000 m2, assuming 1 transmitter per 100-200 m2, the result is 25 to 50 transmitters. This is a sample calculation that illustrates the order of magnitude. The design after the survey may indicate a different value, because it takes walls and structures into account.
What the engineer approves in the design
The layout design contains a plan with marked positions of beacons, nodes and gateways, the number of devices per zone and the assumptions on which the calculations are based. The client's engineer checks whether the positions are accessible, safe to mount and consistent with the zone classification.
Acceptance of the design by the client takes about 2 weeks and is on the critical path: without it mounting does not start. Mounting about 2,000 beacons under the plant's work permit regime then takes about 10 weeks of work by three crews.
Pitfalls of the site survey
The most common pitfall is admitting the supplier's engineer to difficult zones too late, for example warehouses, halls with continuous operation or technical rooms. The second is the gap between the documentation and the actual state: wall changes and refurbishments that are not on the plans.
The third pitfall is the lack of a decision-maker on the plant side. When the design has no owner, acceptance drags on beyond 2 weeks and the schedule shifts by the same amount.
Video
Frequently asked questions
Is a site survey required?
For a large location rollout, yes. Propagation measurements and the layout design are the first stage of the schedule and the basis for the number of beacons.
How many transmitters go into a hall?
As a reference point, 1 transmitter per 100-200 m2 in a building is assumed. The binding number is set by the design after the survey, because it depends on walls and floors.
Does the system need GPS?
No. The position results from the signals of several transmitters averaged on the map, so the system also works where GPS does not reach.