Installing cable-free beacons step by step

InnerWeb beacons are battery-powered, so mounting them requires neither a power supply, nor cabling, nor stopping the installation. This guide describes how the installation crew goes through the hall: from the layout design, through mounting and assignment to points, to the coverage check, and what the client must prepare.

100
transmitters on 8 floors in the patrol pilot
about 10 weeks
mounting about 2,000 beacons by three crews

What distinguishes the mounting of battery beacons?

The InnerWeb industrial beacon runs on a battery. It has no power or network cable, so the crew does not have to run cables, drill openings or switch off circuits. In a patrol pilot, 100 transmitters were mounted on 8 floors without connecting them to power and without stopping the installation.

This has practical consequences for planning. The mounting does not require a service window for the electrical installation, and in many places it also does not require a hot work permit. The beacon has an industrial design, a CE declaration and ATEX execution for zones 2/22, which makes mounting in explosion-hazard zones easier, provided the plant's permit foresees it.

Power and network are needed only by the LoRa nodes and gateways. In a large plant this is about 110 points for about 2,000 beacons, so the vast majority of the elements of the system do not require cable infrastructure.

Step 1: layout design based on a site visit

Mounting is preceded by a site visit with propagation measurements and a layout design. The design indicates where each beacon is to be hung, and the client accepts it within about 2 weeks. Only after the acceptance does the crew start mounting.

Basic rules: in a building 1 transmitter per 100–200 m², on plant roads a transmitter about every 100 m. The exact number depends on assumptions about floors and walls, so it is counted from scratch for the given facility. The system works without GPS, so the transmitters also cover places that the satellite signal does not reach.

Stages of mounting a large number of beacons

Stages of mounting a large number of beaconsBar chart: acceptance of the layout design 2 weeks, mounting about 2,000 beacons 10 weeks.0246810weeksAcceptance of the layout design: 2 weeks2 weeksAcceptance of the layout designMounting about 2,000 beacons (three crews): 10 weeks10 weeksMounting about 2,000 beacons (three crews)
Source: InnerWeb

Step 2: preparation on the client's side

The client's responsibilities cover indicating the mounting places, the 230 V supply and LAN network for the nodes, IP addressing, access to the premises and the people for acceptances. For battery beacons the most important item is access: keys, entry permits and escort in areas with restricted entry.

If work at height requires a lift or scaffolding, it is an element of the mounting plan. The client decides who provides it and enters the tasks into its own permit system.

  • List of mounting places consistent with the layout design.
  • Access to the premises, including restricted areas.
  • Work permits according to the plant's rules.
  • 230 V supply and LAN for the LoRa nodes and gateways, and IP addressing.
  • A person on the client's side for acceptances.

Step 3: mounting and assignment of beacons to points

The crew mounts the beacon in the place indicated in the design. Then it assigns the beacon to a point on the map: it indicates that this particular beacon is in this particular place. Thanks to this, the position of a person, calculated from the signals of many transmitters and averaged on the map, refers to a named location.

Assignment is a step that must not be skipped. A beacon that is mounted but not assigned does not improve the coverage on the map. During mounting it is worth verifying the assignment on an ongoing basis, zone by zone, and not at the end of the whole hall.

How long does the mounting of a larger number of beacons take?

Mounting about 2,000 beacons under the plant's work permit regime takes about 10 weeks of work by three crews. The pace depends on access to the halls and on how many permits the plant issues at the same time.

Step 4: calibration and coverage check

After mounting, calibration zone by zone and accuracy tests follow. The crew walks the routes, checking whether the position on the map matches the real location. Places with insufficient coverage require an additional transmitter or a change of its place.

Finally, training and acceptance take place. The acceptance includes the client's indication of a person who confirms that the coverage matches the design, together with a protocol of the test results.

Checklist

Video

Frequently asked questions

Does mounting beacons require switching off the installation?

No. The beacons are battery-powered and are not connected to a power supply, so in the patrol pilot 100 transmitters were mounted without stopping the installation.

What requires power and network?

The LoRa nodes and gateways, which require PoE power and network. In a large plant this is about 110 points for about 2,000 beacons.

Can beacons be mounted in an explosion-hazard zone?

The InnerWeb beacon has ATEX execution for zones 2/22. Mounting in such a zone takes place according to the work permit and the plant's rules.

Let us plan the mounting in your hall