What changes in the plant and what stays
Passive RFID records a passage through a gate or a read point, not a continuous position, and it requires the tag to be brought close to the reader. After the BLE deployment, the plant still has reads at the gates, but in addition it knows where people are between the read points. The readers do not need to be replaced: InnerWeb is an independent system that complements the client's existing systems, including access control and working time recording.
The role of the existing RFID therefore changes: from the only source of knowledge about presence, it becomes proof of passage, while BLE provides the continuous position. It is worth recording this in the project documentation so that nobody plans to switch off the readers.
Stage 1: setting the tasks and the pilot area
With the head of maintenance, establish which decisions are to use the continuous position: alarms, evacuation, work permits, presence checks in zones. Choose one hall or part of the plant with representative conditions: with racking, partitions and vehicle traffic. A pilot in an area that is too easy gives an overly optimistic result.
Sample work scope across the five transition stages (weeks, sample calculation)
Stage 2: plant map and transmitter placement
The structure of the plant, including buildings, floors and equipment, is drawn in the map editor; the map is built for each facility during the deployment work. Transmitters are placed on the map: on plant roads about every 100 m, and inside buildings at 1 per 100 to 200 m2. For a 4,000 m2 hall this means between 20 and 40 transmitters.
A position on a floor is not given in metres without a source. The documentation of the function rules out such claims, so in the pilot materials describe the accuracy as the result of a measurement, not as a declaration.
Stage 3: installation, register and control route
Transmitters are installed according to the plan from the map, and each receives an entry in the register with a unique pair of identifiers and a recorded position. After installation, walk the control route and review the result: route jumps usually indicate a duplicated identifier or an incorrectly recorded position. Explain them before launching the actual pilot.
Stage 4: pilot with a pass criterion
The pilot is run in the selected area, with a defined group of people and a measurement period. Write the pass criterion as numbers: the median and the 95th percentile of the error on the control route, and the share of correctly indicated zones. The battery life of a device is not a product constant and depends on the configuration, so during the pilot measure its behaviour under the established parameters.
InnerWeb's deployments and pilots to date amount to about 16,000 beacons across 20 deployments and pilots, and all completed pilots went on to deployment. This is the result of our experience, not a promise for every plant, which is why we agree on the pass criterion together before the start.
Stage 5: extension to the plant and maintenance
After the pilot is passed, extension to further halls repeats stages 2 and 3 with the ready register template. Plan maintenance: checking the battery of transmitters and devices, a quarterly review of the register and updating the map after layout changes. Establish who in maintenance owns the transmitter register, because without an owner the register starts to drift after the first rebuild.
Most common pitfalls
Three pitfalls recur during the transition: a plan that is too general, no owner of the register, and no numerical criterion. The first leads to a pilot in an area that does not represent the plant. The second leads to duplicated identifiers after the first changes. The third leads to a dispute over whether the pilot succeeded.
It is also worth agreeing from the start how the change is communicated: who informs employees about location devices, what data is recorded and for what purpose. A team that understands the purpose of location is more willing to carry the device and reports problems faster, which translates into the quality of the pilot data.
- A pilot in an area that is too easy, without racking and vehicle traffic.
- No single owner of the transmitter register in maintenance.
- No numerical pass criterion for moving to deployment.
- Assuming that the RFID readers will be switched off.
Video
Frequently asked questions
Do the RFID readers at the gates need to be replaced?
No. The readers stay, because the card swipe is the proof of passage. InnerWeb complements the existing system and does not replace access control readers.
How many transmitters are needed for a pilot?
It depends on the area: under the rule of 1 transmitter per 100 to 200 m2, a 4,000 m2 hall needs between 20 and 40 units.
How do you measure whether the pilot succeeded?
Set the numbers before the start: the median and the 95th percentile of the error on the control route, and the share of correctly indicated zones. A declaration of satisfaction should not decide the move to deployment.
What to do with transmitters after the hall layout changes?
Update the map and the register within the same order, and after the change walk the control route to catch route jumps.