Ex Zone Classification Before Selecting a Beacon: What to Prepare for the Integrator

Before the integrator indicates mounting places for ATEX beacons, the explosion protection specialist has to provide a complete set of information about the zones. We explain which documents, in what order and with which pitfalls. We do not replace the classification project; we show the point where it meets the selection of equipment.

25 to 35 PLN
estimated own cost of a standard beacon
Source: card
about 75 PLN
estimated own cost of an ATEX beacon
Source: card

Why classification comes first

The ATEX beacon is approved for zones 2 and 22. For zones 1 and 21, certification is commissioned for the needs of the client's installation, with no promised date. This means that the range of places where the ATEX version is sufficient follows from the zone classification of the plant, not from the equipment catalogue.

The range of zones for beacons has to be verified against the zone classification project of the plant. The integrator has neither the authority nor the knowledge to classify the zones of a plant. Its task is to use the result of the classification to select the version and the mounting places.

What the explosion protection specialist delivers

The integrator needs material that can be drawn onto the hall plan. A verbal description alone is not enough, because the placement of beacons is based on a grid of points and a plan view.

Deliver the package to the integrator in one go, not piece by piece. Every later change of zones moves the mounting places and may change the number of beacons in the ATEX version.

  • current zone classification document with drawings of halls and yards
  • marking of zones 2 and 22, and any zones 1 and 21, on the floor plans
  • information on the gas group and temperature class, if it affects the selection
  • list of sources of hazard and technology changes planned during the implementation period
  • contact to the person authorised to answer questions about the zones
  • date and version of the document, to avoid working on an outdated drawing

Own cost of beacons in a sample hall (PLN)

Own cost of beacons in a sample hall (PLN)Bar chart: 1,140 PLN with 8 ATEX and 18 standard beacons, 1,950 PLN with all beacons in ATEX.0500100015002000PLN8 ATEX and 18 standard: 1140 PLN1140 PLN8 ATEX and 18 standardAll 26 in ATEX: 1950 PLN1950 PLNAll 26 in ATEX
Source: Sample calculation: 30 PLN standard, 75 PLN ATEX, 26 beacons

How the integrator uses this data

First it draws the zones onto the drawing with the beacon grid. For each point it checks whether it lies in a zone requiring the ATEX version. Points in zones 2 and 22 receive the ATEX version, the others the standard version.

If a point falls in zone 1 or 21, the integrator has three options: move the point outside the zone, keeping the coverage thanks to the signals of neighbouring beacons; commission certification for the needs of the installation; or give up coverage of that place. The decision is taken by the plant together with the explosion protection specialist.

Sample calculation: the cost difference between versions

In the comparative calculation, the own cost of a standard beacon was estimated at 25 to 35 PLN, and of an ATEX version at about 75 PLN. This is an estimate, not a price list; individual quotation applies.

Assume a hall with 26 beacons, of which 8 lie in zones 2 or 22. With an assumption of 30 PLN for standard and 75 PLN for ATEX, the own cost is 18 x 30 plus 8 x 75, that is 540 plus 600, in total 1,140 PLN. If all 26 were ATEX, the cost would be 1,950 PLN. The difference of 810 PLN shows that classification before selection has a financial dimension, although safety decides.

Implementation pitfalls

The most common problem is a change of classification during implementation, because the plant rebuilt the installation and the drawing was not updated. The second is the assumption that the ATEX range covers everything hanging in the hall.

The third problem is the lack of a record in the as-built documentation of which beacons work in which zones. It is worth entering this into the acceptance protocol and into the equipment register, so that at a rebuild it is possible to check quickly what to change.

Example calculation

Own cost of beacons after zone classification

Assumptions
ParameterValue
Number of beacons26 pcs
Beacons in zones 2 or 228 pcs
Own cost of standard30 PLN
Own cost of ATEX75 PLN

Result: 18 x 30 plus 8 x 75 gives 1,140 PLN, and 26 x 75 gives 1,950 PLN; the difference is 810 PLN.

Note: Sample calculation based on own cost estimates; it is not a price or an offer, individual quotation applies.

Video

Frequently asked questions

Does InnerWeb classify Ex zones?

No. Classification is the task of the plant and an authorised specialist. InnerWeb uses its result when selecting the version and the mounting places.

What about a beacon in zone 1 or 21?

The ATEX version is approved for zones 2 and 22. For zones 1 and 21, certification is commissioned for the needs of the client's installation, with no promised date.

What if the classification changes after installation?

The register of beacons and their zones is reviewed, and places that do not match the new classification are moved or replaced with the appropriate version.

Let us start with the list of zones

Talk to the InnerWeb team about what to hand over to the integrator before selecting ATEX beacons. We will help you put together the list of documents.