Why the site visit is the gate of the project
The transmitter layout rests on general rules: on plant roads about every 100 m, inside buildings 1 transmitter per 100 to 200 m2, and in halls a design assumption of 1 point per 225 m2. These rules require validation on site, and BLE range in steel and reinforced concrete structures is verified by measurement on site before the final placement of transmitters.
The site visit turns assumptions into data. The integrator leaves it with a list of points confirmed by measurement, a list of points to densify, a schedule of hard-to-reach places and information on Ex zones. Without this, the project is a sketch.
What to check in the hall
In the hall, what cannot be seen on the floor plan is the most important: the position of cranes and rails, steel structures, stored loads and the places where workers actually spend time. A plan does not show how many transmitters will be audible at a given point, and that number of audible transmitters is what decides the quality of the position.
Measurement and geometry
Range is measured at points representative of different types of structure, and the results are marked on the plan. Attention goes to places behind cranes, next to furnace walls, under platforms and in narrow corridors between technological lines.
Floors and platforms
Receiving points are counted separately for each floor, with a reserve added for hard-to-reach places. During the visit it is checked how platforms block the view of the hall and whether a transmitter mounted at platform level will be audible from the floor.
Starting rules of the layout to be confirmed on the visit
What to check outside and in Ex zones
Outdoors, transmitters are installed only where there is power, that is on building walls and lamp posts, without new poles and cables. The visit therefore establishes where such points already exist and whether their spacing approaches about 100 m.
In explosion-hazard zones the plant's zone classification has to be verified. Transmitters in the ATEX version are approved for zones 2 and 22; certification for zones 1 and 21 is commissioned for the client's needs, with no promised lead time. The Ex zone range for the transmitters has to be checked against the plant's zone classification project before the choice of version is made.
How to close the site visit
A good visit ends with a document: a plan with points marked, the measurement result for each zone, a list of points to densify compared with the starting rules, a list of hard-to-reach places with service constraints and information on Ex zones. Only this set allows the design to be frozen, and then, after installation, a coverage measurement is made and attached to the acceptance protocol.
Checklist
Video
Frequently asked questions
Does the site visit replace the range measurement?
No. The measurement is its main element. The layout rules are assumptions, and the measurement in the hall confirms or corrects the grid.
Who takes part in the visit?
The integrator, a representative of maintenance, the OHS or security function, and a person who knows the plant's Ex zone classification.
Do new poles have to be erected outdoors?
No. Transmitters are installed where there is power, that is on building walls and lamp posts.
What comes after the visit?
Freezing the layout design, installation, a coverage measurement after installation, and attaching the result to the acceptance protocol.
Let's arrange a site visit at your plant
InnerWeb will prepare a plan for the visit and the range measurement, so that the transmitter layout is frozen on data, not on assumptions.