What the ATEX design for zones 2/22 covers
The InnerWeb industrial beacon has an industrial design, a CE declaration and an ATEX design for zones 2/22. Zone 2 concerns a gas atmosphere in which an explosive mixture appears rarely and briefly, and zone 22 is the analogous category for dusts. It does not cover zones 0, 1, 20 and 21, for which other equipment categories are required.
For the health and safety manager the conclusion is practical: before talking to the supplier you need a current classification of zones in the facility. Without it, you cannot reliably say which of the mounting places fall within the scope of the design.
Stage 1: classification and mounting plan
Start from the explosion protection document and the zone plan. Mark the proposed beacon mounting places on this plan. In a warehouse where only a fragment is an Ex zone, it is useful to draw a two-colour map: ordinary places and places within the zone.
The density rule is the same as for the rest of the facility: one beacon per 100 to 200 m2 inside a building, and about every 100 m on site roads. An Ex zone does not change the number of beacons needed for location; it changes the type of device that may be mounted.
Split of beacons in a warehouse (example: 30 pcs, 8 in the Ex zone)
Stage 2: choosing the equipment
In zone 2 or 22 you mount beacons with the ATEX design; outside the zone the standard design can be used. Mixing both designs in one facility is permissible and often economical, but it requires markings in the documentation and in the identifier table, so that service does not replace a device with the wrong one.
With such a division it is especially important to keep major:minor identifiers unique. Two physical beacons with the same identifier will be recognised by the system as one entry, and a vehicle near each of them will be placed at one stored location, which produces route jumps visible on the map.
Stage 3: mounting and acceptance
Mounting in an Ex zone is carried out by authorised persons, in accordance with the device instructions and the facility documentation. After mounting, perform a control walk with a phone: check that all beacons are detected and that the route has no jumps.
Attach to the acceptance documentation a table with: identifier, mounting place, device design, zone. Such a table is evidence for an auditor and the basis for later inspections, but it is not a declaration of conformity of the whole installation.
Pitfalls we see most often
The first pitfall: assuming the whole warehouse is an Ex zone because someone once described it that way. Over-classification raises the cost, and updating the documentation is often cheaper than more expensive devices.
The second: underestimating, because the classification does not reflect new materials stored after a change of product range. The third: replacing a device during service without checking whether the place is within the zone. The fourth: a beacon position stored in the database in centimetres, while the map displays it divided by 100, which, when entering values by hand, produces an error of an order of magnitude.
Video
Frequently asked questions
Is the InnerWeb beacon suitable for zone 0 or 1?
The ATEX design of the beacon covers zones 2 and 22. Higher-risk zones require equipment of another category, so this needs a separate analysis.
Does an Ex zone require more beacons?
No. The density rule is the same. What changes is the type of device mounted in the zone.
Does the installation table replace a declaration of conformity for the installation?
No. It is evidence for an audit of the devices and mounting places, but the assessment of the whole installation belongs to authorised persons.