Transmitter network acceptance checklist after installation

The inspector or project manager has one chance to check the transmitter network before the alarms are switched on: after installation and before SOS and notifications go live. The list below orders the acceptance in the sequence in which faults tend to appear, and indicates the evidence worth recording for each point.

Why is acceptance carried out before the alarms?

Coverage of the transmitters is calibrated at the start of the deployment, before the alarms are switched on. An alarm switched on over an unfinished network can generate false events or, worse, fail to work in a place without coverage.

Acceptance closes the installation stage and is evidence that the network meets the design assumptions. The acceptance protocol goes into the documentation and serves as a reference point for later inspections.

Coverage and placement

The first block concerns the placement itself. Compare the actual positions of the transmitters with the design: in a building there should be 1 transmitter per 100 to 200 m2, and on plant roads the spacing should be roughly every 100 m.

Walk a control route with a phone and observe whether the position follows you without stalling. The position results from the signals of many transmitters averaged on the map, so at every point on the route the phone should hear several of them.

  • Number and position of transmitters consistent with the design.
  • Control route without stalling or position jumps.
  • Shadow zones marked and described in the protocol.

Number of control items in each acceptance block

Number of control items in each acceptance blockHorizontal bar chart: 3, 3, 2 and 3 control items in the four blocks0123itemsCoverage and placementCoverage and placement: 3 items3Identifiers and dataIdentifiers and data: 3 items3Power calibrationPower calibration: 2 items2Documents and rangeDocuments and range: 3 items3
Source: Summary of the checklist items on this page

Identifiers and positions in the data

The second block is the data. Two physical transmitters with the same identifier, several hundred metres apart, produce one position in the system, so uniqueness of identifiers is checked during installation, not after the first error.

Also check that each transmitter is assigned to the correct facility in the data. Beacons located on a road but assigned to a warehouse draw a jump on the route. A wrong position is corrected once for all future routes.

The application accepts only transmitters with the manufacturer's identifier, and a foreign transmitter is rejected. During acceptance it is worth checking that there are no devices outside the set in the network.

Power calibration and coverage

The third block concerns power. Calibrating the transmission power to the hall reduces interference and extends battery life. The result is recorded in the protocol, because battery life is planned after calibration, not according to factory settings.

Battery life is not given as a guarantee, so the protocol does not contain a promise of a number of years. It records the starting state against which maintenance monitoring is referenced.

Documents and range

The fourth block covers documents and range. For hazardous zones check the complete set: the CE declaration and the ATEX document, in which the scope of certification is zones 2 and 22. Attach them to the acceptance protocol.

Also verify that network coverage exists across the whole area in which the alarm operates. Alarm and SOS do not work outside coverage without a separate coverage solution, so places without coverage must be described and secured by another method.

How do you record the acceptance result?

Enter in the protocol the result of each point, the date, the person accepting and any remarks. A point that is not met ends with a corrective task with a deadline, and final acceptance takes place only after all corrections are closed.

The alarms are switched on only after acceptance. It is worth repeating the acceptance result after the first maintenance inspection, to confirm that the network has not changed its parameters.

Checklist

Video

Frequently asked questions

Who should accept the transmitter network?

The inspector or project manager on the plant side, with the participation of the installer and the integrator. Both sides sign the protocol.

Can acceptance be carried out after the alarms are switched on?

It is not recommended. An alarm on an unverified network may give false events or fail to work in a zone without coverage.

What should be done about a place without coverage?

Describe it in the protocol and secure it with a separate coverage solution, because alarm and SOS do not work outside network coverage.

Is acceptance repeated later?

It is worth repeating it after the first maintenance inspection to confirm the state of the network.