Transmitter grid in a hall and on platforms: how to count it step by step

In a multi-level plant, the transmitter grid is counted separately for the hall, platforms, stairwells and plant roads, not with a single density for the whole building. This guide walks through five steps with a numerical example and indicates which assumptions must be confirmed by measurement on site before the integrator freezes the design.

42
points in the example of a 5,400 m2 hall with platforms
Source: sample calculation
15 m
grid for a hall and step for a platform
Source: product card

Step 1: split the facility into counting zones

The first mistake in designs is one density for the whole. A heavy plant consists of elements with different characteristics: an open hall, platforms and galleries, stairwells, technical rooms and the roads around the buildings. Each of them is counted under its own rule, and the results are added up.

Receiving points are counted separately for each floor, with a reserve added for hard-to-reach places, instead of applying one uniform grid. A floor plan from another level is not a basis for counting, because the slab structure and the position of walls change the range.

Step 2: count the hall

The design assumption for a hall is 1 point per 225 m2, which means a grid of about 15 m, with a minimum of four points. In a steel hall the density follows from BLE range in the presence of metal structures, and two points on opposite edges do not replace a grid. The position is built from the signals of several transmitters, so at every workplace several of them should be audible.

Example: a hall measuring 60 by 90 m has 5,400 m2. Dividing by 225 gives 24 points. This is the starting figure, which is verified by a range measurement before installation.

Structure of the 42 points in the sample grid

Structure of the 42 points in the sample gridPie chart: 24 points for the hall, 8 for platforms, 6 for stairwells, 4 for the reserveHall: 24 points (57.1%)Platforms: 8 points (19%)Stairwells: 6 points (14.3%)Reserve: 4 points (9.5%)42pointsHall24 points (57.1%)Platforms8 points (19%)Stairwells6 points (14.3%)Reserve4 points (9.5%)
Source: Sample calculation based on the assumptions of 1 point per 225 m2 and 1 point per 15 m of platform

Step 3: count the platforms

For platforms the assumption is 1 point per 15 m of walkway. A platform is narrow, so counting it by area would give an understated result, and the worker's position on a platform must be distinguishable from the position on the floor below.

Example: two platforms of 60 m each give 120 m of walkway, which is 8 points. Transmitters are mounted so that their signal is audible at platform level, not only from the floor of the hall. This is verified in the measurement.

Step 4: add stairwells and the reserve

Stairwells and passages between floors are places where location must decide which floor the person is on. For each floor, a separate point is therefore planned. The example assumes two stairwells and three floors, which gives 6 points.

The reserve for hard-to-reach places protects against the results of the measurement. In the sample calculation, a reserve of 10% of the total is assumed: (24 + 8 + 6) = 38 points, a reserve of 4 points, 42 points in total. The percentage of the reserve is a sample assumption that the plant adjusts after the measurement.

  • hall of 5,400 m2: 24 points,
  • platforms of 120 m: 8 points,
  • stairwells: 6 points,
  • 10% reserve: 4 points, 42 in total.

Step 5: verify on site and add the plant roads

BLE range in steel and reinforced concrete structures is verified by measurement on site before the final placement of transmitters. The measurement result may force a tighter grid behind a crane, where the density of structures is high, or in places where a platform blocks the view of the hall. The rules from steps 2 to 4 are design assumptions that require validation on site.

Plant roads around the hall are added separately: transmitters are placed on them about every 100 m. Outdoors, transmitters are installed only where there is power, that is on building walls and lamp posts, without new poles and cables, which limits cost and implementation time.

What to record in the project documentation

The placement design should include a plan with point numbers, the mounting height, the floor, information on power supply and the measurement result for each zone. After installation, the coverage measurements are attached to the acceptance protocol. The documentation is also the basis for service: when cells are replaced, the transmitter must be found in the same place where it is recorded in the database.

Checklist

Video

Frequently asked questions

Is the 15 m grid a binding standard?

No. It is a design assumption that requires validation on site. The final grid is set by a range measurement in the specific hall.

Why are platforms counted separately?

They are narrow, and the position on a platform must be distinguishable from the position on the floor. Counting by area would understate the result.

Do outdoor areas need new poles?

No. Transmitters are installed where there is power, that is on building walls and lamp posts, without new poles and cables.

How big is the reserve?

In the example it is 10%, as a sample assumption. The actual value is set after the range measurement.

Let's calculate the grid on your floor plans

Send us the plans of the hall, the platforms and the floors. InnerWeb will prepare a preliminary grid and a range measurement plan before installation.