Why mounting height is a service decision
A beacon works for several years, but its cells have to be replaced eventually. Cell replacement is a service task, and in one of the maintenance offers it was included in the subscription about every 4 years. If a beacon hangs at a height that can only be reached with a lifting platform and while the hall is running, each replacement becomes an operation with risk.
That is why height and fixing element are chosen not only for coverage, but also for service access. This is a decision taken jointly by the integrator, maintenance and occupational health and safety, before the equipment is ordered.
Practice 1: mount on fixed elements
The best places are girders, columns and walls, which do not change their position. A beacon hung on a moving structure or on a cover that is removed no longer matches its record on the map.
Before choosing a point, check whether service access exists during a shutdown: a platform, lockable doors, room for the lifting platform. If not, move the point to an accessible place, keeping the grid.
Components of a sample maintenance subscription (PLN net per month)
Practice 2: count levels and the reserve
Receiving points are counted separately for each level, and a reserve for difficult places is added instead of applying one uniform grid. Mounting at height usually concerns the upper level and the mezzanines.
Mark on the plan the points that cannot be reached without scaffolding, and treat them as reserved for a shutdown. If such a beacon fails, neighbouring points keep the position, because the position is calculated from many beacons.
Practice 3: write the replacement into the service contract
A sample maintenance subscription covered 200 beacons at 7 PLN, a server and licences for 800 PLN, and the rental of 2 watches at 100 PLN each, giving a total of 2,400 PLN net per month. These are indicative ranges from implementations in 2025 and 2026; individual pricing applies.
Pay attention to what such an item covers: cell replacement, replacement of a damaged beacon, a coverage check. It is worth recording that the replacement takes place during a shutdown, not on an arbitrary day.
Practice 4: keep the record up to date after replacement
After replacing a beacon or moving it, update the record in the database and check the route. A beacon recorded in the wrong place draws a route jump, and two physically different beacons with the same identifier are recognised as one entry.
Introduce two control actions after each replacement: a comparison of the physical label with the entry, and a short drive or walk along the route where the point lies. This takes a few minutes and saves hours of diagnosis.
Practice 5: plan the replacement schedule in advance
The choice of broadcast interval affects the date of replacement: 500 ms means 4 to 5 years, 250 ms about 3 years, 150 ms about 2 years. If the plant has a yearly shutdown, set the interval so that the next replacement falls in one of them with a margin.
Group the beacons by height and access, so that one crew with one lifting platform replaces them in one window. A scattered schedule generates more visits than a single action.
Checklist
Video
Frequently asked questions
Does replacing cells require stopping the hall?
It depends on the height and place. For points on platforms and in traffic zones replacement is planned during a shutdown, while easily accessible points can be serviced during operation with the observance of occupational health and safety rules.
How often do the cells need to be replaced?
It depends on the broadcast interval: 4 to 5 years at 500 ms, about 3 years at 250 ms and about 2 years at 150 ms.
Is cell replacement included in the subscription?
In one of the maintenance offers the replacement was included in the subscription about every 4 years. The scope is always agreed individually.
Let us agree on service at the design stage