The problem: an offer based on an estimate
An offer before installation rests on an estimate, and the estimate depends on the plans. In an example geometric calculation for about 118 thousand m2 of built-up area, the result was 1,875 indoor and 156 outdoor transmitters, and 2,000 was adopted. The number of floors in the main building had the largest effect on this result, and the difference between 4 and 8 levels is about 360 transmitters.
If the bidder assumed 4 levels and there are actually 8, the offer will be short about 360 transmitters. If the bidder assumed 8 and there are 4, the client pays for the surplus. Both situations spoil the comparison, because the final price is then not a feature of the offer but a consequence of the assumptions.
The solution: settlement based on the status after installation
Settling transmitters by the actual status after installation, rather than by the estimate in the offer, limits the risk of wrong assumptions about floors. The unit price is fixed, and the number of units follows from the protocol after installation. The risk of the plan no longer sits on one side only.
- in the offer, show the unit price of the transmitter, installation and configuration separately
- record the estimated number of units as an indicative value, not as a commitment
- define the counting method: 1 unit per 150 m2 per floor, with stairwells, lifts and galleries counted separately
- set the protocol after installation as the basis for settling quantities
- record an upper limit above which the client's approval is required
Quantity risk: estimate in the offer versus the range after installation (8 floors)
- Lower limit
- Upper limit
How to compare two offers based on different assumptions
For the comparison to make sense, bring both offers to a common number of floors. Use the base and extreme variants: for 4 and 8 levels in the example this gives 360 and 720 transmitters, and with the plus or minus 30 percent margin the ranges are 252-468 and 504-936. Then multiply the quantities by the unit prices of both bidders.
This test often changes the order of the offers. An offer with a lower total price at the 4-level assumption may turn out more expensive at 8 levels if its unit price is higher. Only the table of variants shows which offer is robust against an error in the assumptions.
Risk calculation without quoting prices
Unit prices depend on the execution, the zone and the power supply, and this article deliberately does not give them. The risk can still be calculated in units: with a base of 720 transmitters, the plus or minus 30 percent margin is 216 units up or down. Purchasing can multiply this by its own price from the offer and record it as a conditional reserve.
A conditional reserve is not an expense until the protocol after installation confirms it. In this way the budget includes the upper limit, and the client does not pay for transmitters the building does not need.
What to put in the contract so that settlement works
Settlement after installation requires three provisions. First, a definition of the settlement unit, for example a transmitter installed and confirmed in the map editor on the correct floor. Second, a deadline for the protocol after installation. Third, a procedure when the upper limit is exceeded, for example pausing installation until the client decides.
It is also worth recording that the data for the map editor, meaning the plans and floor names, is provided by the client, and that the contractor reports discrepancies within a set deadline. This reduces disputes about whose assumption was wrong.
Quantity margin with uncertain floors
| Parameter | Value |
|---|---|
| Transmitters per floor (example assumption) | 90 units |
| Number of floors in the estimate | 8 floors |
| Base result | 720 units |
| Result margin | 30 percent |
Result: The margin is 216 units, so the actual transmitter count falls within the range 504-936. Settlement after installation moves the difference from the estimate to the actual status.
Note: Example calculation based on the assumptions above, without prices. Indicative ranges from 2025-2026 deployments; individual quotation.
Video
Frequently asked questions
Is settlement after installation a requirement?
No, it is a purchasing practice that limits the risk of wrong assumptions about floors. The parties may also agree on a lump sum if the plans are complete and the margin is small.
Who is responsible for wrong plans?
It depends on the contract. It is worth recording who provides the plans and the floor names, and the deadline for the contractor to report discrepancies.
Is an upper limit of units necessary?
It is definitely worth having. The limit protects the budget and forces the client's decision when it is exceeded, instead of the scope quietly growing.