Why acceptance is done on foot
A person's position is calculated from the signals of several transmitters and averaged on the map, and the system works without GPS. This kind of location has to be checked in the field, because a plan on paper will not show whether the signal from the floor above or below outweighs the signal from one's own floor. A walk shows this in a few minutes on each level.
In the building the rule of 1 transmitter per 100 to 200 m2 is applied, and in the geometric method 1 unit per 150 m2 per floor. Acceptance confirms that the density adopted gives an unambiguous floor at every point, including the critical places.
Order of the walk: from the ground floor through the stairwell
Start at the ground floor and move floor by floor, using the stairwell between floors. Stairwells, lifts and galleries have their own transmitters, so that is where a wrong floor assignment is most likely. On each level walk the corridor, several rooms and the area around the stairwell.
On the online map check two things. First, whether a double click on a person opens the building on the correct floor. Second, whether the level selector shows the expected number of levels, since it appears only with at least two levels, and the labels are P, 1, 2 and so on.
Density of transmitters in building interiors
What to confirm on the map during acceptance
Acceptance is complete only when the map behaves in line with reality. The system determines a person's level in turn from the level of the location, then the line, then the area. If the first source is not filled in, the result rests on the next one, so the data must be consistent on all levels.
Entering a level from the online map works only when linking building volumes to area data is switched on. This is off by default, so the person accepting should check this setting at the start of the walk, before looking for errors in locations.
What to record in the protocol
The acceptance protocol should contain a list of levels with a compliance rating, notes on stairwells and lifts, and a list of transmitters to be corrected. This makes it possible to settle the installation on the actual state after installation, which limits the risk of wrong assumptions about floors.
Attach screenshots from the online map for each floor and a note of who accepted and when. Such a document is evidence for audit and a point of reference for later changes to the building.
Checklist
Video
Frequently asked questions
Does acceptance require special equipment?
No. A device that shows a person's position on the online map and access to the map in view mode is enough. The whole process is a control walk with the results noted down.
What if a person appears on the wrong floor?
Note the place and check the level assignment of nearby transmitters in the editor. The most common causes are a wrongly assigned transmitter in a stairwell or a lift without its own transmitter.
Does acceptance need to be repeated after changes to the building?
It is worth repeating it for the changed levels, for example after adding a mezzanine or rebuilding a stairwell. A full walk makes sense for larger changes to the layout.