The problem: hazards repeated on the print
In a moulding plant the same hazards apply to the whole hall: moving cranes, slippery floors after oil leaks, hot surfaces. When every machine has its own copy of these entries, the permit print swells, and the important risks specific to a given machine get lost among the repetitions.
The solution is structure: a risk is entered once, at the level it applies to, and the system assembles the print from all the right levels without repetitions.
Five sections of the print with deduplication
The risks on the permit print are assembled in five sections with deduplication. Understanding these sections is the basis of a good catalogue, because it shows where health and safety should place a given hazard.
If the same risk exists at several levels, the print shows it once. As a result the catalogue can be built generously, without fear that the print becomes unreadable.
- Risks common to several permits
- Hierarchy: hall, area, line, location
- Additional locations, if the work covers several places
- Type of particularly dangerous work, for example hot work
- Risks added by the issuing person to a specific permit
Risk level thresholds
How to plan the hierarchy in a moulding plant
At the hall level place general hazards: internal transport traffic, noise, crane operation. At the area level, for example the resin drying zone, enter dust and temperature risks. At the line and single machine level leave the specific hazards: hydraulic pressure, mould movement, hot nozzles.
A practical rule: if a hazard applies to more than half of the machines in an area, its place is higher in the hierarchy. As a result, a change to one entry updates all the permits in the area.
Risk editor and assessment after protective measures
The risk editor lets the administrator and health and safety add a missing risk once, after which it can be selected by everyone who issues permits. A shift supervisor who notices a new hazard reports it to health and safety, rather than writing it in their own words on every permit.
In the risk assessment after protective measures, usually only the probability falls, while exposure and severity stay unchanged. The risk level thresholds are 20, 70, 200 and 400. It is worth remembering when assessing: a protective measure that does not change the severity will not change the risk class below the threshold without a reduction in probability.
Keeping the catalogue up to date
The catalogue needs a review after every incident and after every change to the hall layout. A quarterly review with the participation of shift supervisors catches risks that have appeared in practice more often than expected. InnerWeb is a software vendor and integrates with the plant's existing systems, so the catalogue develops independently of the machines.
Checklist
Video
Frequently asked questions
Will the same risk appear several times on the print?
No. Risks assembled in the five sections are deduplicated, so the print shows each one once.
Who can add risks to the catalogue?
The administrator and health and safety through the risk editor. Once added, the risk can be selected by everyone who issues permits.
What are the risk level thresholds?
20, 70, 200 and 400.