Why the requirements must be in the body of the request
A contractor prices what is in the request. If the requirement for training, valid qualifications or a permit before entry appears only in the site entry rules, the contractor has not included it in the price or the schedule. A dispute over time and cost follows, and under pressure from a shutdown the plant gives in.
For a wood plant, combustible dust adds another dimension: a service for dust extraction, dryers or machines may require hot work or entry into an installation, and those are particularly hazardous tasks with their own requirements.
Recommendations for the purchasing department
The following recommendations concern the content of the request and the contract. Each can be checked by the plant during the work.
- a requirement for valid qualifications, medical examinations and training of the contractor's staff before entry, with the plant able to verify them,
- a commitment to work on a single permit that is visible to the issuer on the plant side and to the contractor,
- approval of particularly hazardous work only by a user on the plant side,
- a clause on the observation period after hot work and the blocking of permit closure,
- the plant's right to suspend a permit without claims for downtime on the contractor's side,
- rules for visits without work: talks, quotes and measurements during a planned visit with a host on the plant side.
Example weights of criteria for assessing service offers
Qualifications and entry to the plant
The system stores the qualifications, medical examinations and training results of workers and, when a permit is created, checks whether the assigned workers hold the required and valid qualifications. For purchasing, this means that the contract can require the data about the people to be delivered before entry, and the plant can check it in one place.
A planned visit by an external firm replaces the permit for one day for people who do not work, for example for a talk, a quote or measurements, but training, qualifications and an active account still decide whether a person may enter. The visit has a host, whom the system calls once when the person first enters. It is worth describing this in the request so that the bidder does not confuse a visit with work.
Permit and post-work period clauses
A permit issued to an external firm is handled on one permit, and only a user on the plant side can approve work classified as particularly hazardous. The request should state that the contractor does not start work before approval and that waiting time is not a basis for claiming additional payment.
For hot work the system enforces an observation period after the work, in two stages, 1 h and 4 h, carried out by a fire watch on the contractor's side, and closing is blocked until at least 3 hours of monitoring have elapsed. The contractor should include this time in the schedule and in the price, and this is the argument for writing it into the request.
How to assess offers against these requirements
A comparison table of offers should have separate columns for staff qualifications, permit rules, the post-work period and suspension conditions. An offer that omits these columns is not cheaper: it is a cost shifted onto the plant.
It is also worth asking the contractor about experience in plants with combustible dust and about who on its side will act as the fire watch. The answer says more than a declaration about a quality system.
Video
Frequently asked questions
Must a visit before the offer be billed as work?
No. A planned visit replaces the one-day permit for people who do not work, but training, qualifications and an active account still decide whether a person may enter.
Who can approve particularly hazardous work by a service firm?
Only a user on the plant side. The contractor sees the same permit but does not approve it.
Can the post-work period for hot work be shortened in the offer?
Not as part of the offer. Closing hot work is blocked until at least 3 hours of monitoring have elapsed, so the contractor should include this time in the schedule.
Sources
OHS requirements in the request for quotation
We will help turn the permit and qualification functions into clauses of the request for service firms at your plant.
Let's talk