Starting situation at the plant
The furniture plant runs a dust extraction system serving several panel and solid wood machining stations. The bag filter, ducting and cyclone need periodic repairs, and some of this work is done by an external firm, often using an angle grinder or welding equipment. Wood dust is combustible, so any spark near deposits is a real hazard, not a formality.
The maintenance manager has two concerns. The first: the permit is prepared by the contractor, and the plant learns about it only when the crew is already standing at the installation. The second: once welding ends, everyone wants to return to production, and the observation period after work is cut short for lack of time. The scenario below answers both.
One permit visible to both sides
In the scenario described here, the work permit for an external firm is handled on a single document: the plant's issuer and the contractor see the same data, without retyping content between systems. Work classified as particularly hazardous is a separate object in InnerWeb, attached to the permit, with its own state machine, and only a user on the plant side can approve or reject it. The rule is enforced in code, so it does not depend on the goodwill of the contractor.
Before a permit is issued, the system checks whether the assigned workers hold the required and valid qualifications, medical examinations and training results. The manager does not have to request scans: a missing valid qualification appears as a warning when the permit is created.
Hazards assigned to the location
A catalogue of hazards with the required protective measures can be assigned to a location, to a type of hazardous work, and supplemented ad hoc by the issuer. For a dust extraction installation this means that the hazard of dust deposits and the protective measure, for example removing the deposit before work, enter the permit automatically, because they follow from the location. The issuer's ad hoc addition covers what the catalogue did not anticipate.
Time thresholds after hot work
Hot work and the post-work period
For hot work, the system enforces an observation period after the work ends, in two stages, 1 h and 4 h, carried out by a fire watch on the contractor's side. Closing the hot work task is blocked until at least 3 hours of monitoring have elapsed. For the manager this means that nobody can close the permit early, even if the crew is packed up and the issuer is in a hurry.
In a wood processing plant the post-work period matters in particular, because a smouldering spot can hide in dust deposits and show up after a long time. A record of observations with the time and the person gives evidence for an audit and for a conversation with the fire service, should an incident occur.
- stage 1: observation for 1 h after the end of hot work,
- stage 2: observation for 4 h after the end of the work,
- closing blocked until at least 3 hours of monitoring have elapsed,
- a fire watch on the contractor's side as the person responsible for observation.
Suspending the permit when conditions change
A user on the plant side can suspend an active permit. The suspension blocks closing tasks other than the unblocking tasks listed by the person who suspended it. Example: during the repair, the work at the neighbouring station changes and dust levels in the hall rise. The manager suspends the permit, and the contractor can close only the safety actions, for example shutting down the burner, which were marked as unblocking.
This is useful where the plant does not want to settle a dispute by phone: the permit status is visible to both sides and changes in one place.
The picture on the hall map and conclusions
A permit covering a chain of equipment, for example a cyclone, ducting and a filter, is drawn on the map as one outline on the hall plan. After the location is recognised, the system adds the worker to the permits for the place of work or removes them from those permits, so the fire watch and the issuer can see who is actually at the installation. The worker carries a BLE device, and the platform knows the position from the signal strength of the transmitters it hears.
Conclusions for a furniture plant: permit and qualifications in one place, a post-work period enforced by the system, suspension available to the plant, the outline on the map visible to everyone. None of this requires replacing systems, because InnerWeb is an independent system that complements the client's existing systems and works without GPS.
Video
Frequently asked questions
Can the service firm approve its own permit?
No. Only a user on the plant side can approve or reject work classified as particularly hazardous, and the rule is enforced in code. The contractor sees the same permit and carries out the post-work observation.
Can the post-work period be shortened during a shutdown?
Closing hot work is blocked until at least 3 hours of monitoring have elapsed. Shortening it would therefore mean changing the plant's rules, not making a decision under time pressure on the shop floor.
Is it necessary to replace the plant's systems?
No. InnerWeb is an independent system that complements the client's existing systems and works without GPS. Qualifications and permits are handled in InnerWeb itself.
Sources
Let's talk about permits for service firms
We will show, using a wood processing plant as an example, how a single permit seen by the plant and the contractor works together with the post-work period.
Let's talk