Parallel Period With Paper: Recommendations for the Plant Director

The parallel period is the time when the plant keeps paper alongside the system. Too short a period risks gaps in documentation, too long doubles the work and teaches people that the system is unnecessary. The recommendations below help set the length, responsibility and criteria for stopping paper.

60 h
extra work in the parallel period in the example calculation
Source: example calculation

Who this is for and why a parallel period

The typical starting point at a plant is work permits on paper and in Excel sheets, companies invited by different people, and training validity tracked by hand. After the pilot starts, the plant director faces a decision: stop using paper immediately or keep it for some time. These recommendations concern this decision.

InnerWeb works as an independent system supplementing the client's existing systems (access control, time attendance, HR, ERP), so the migration does not require switching these systems off. This eases the risk: the parallel running concerns BHP documents and permits, not the whole infrastructure of the plant.

Recommendation 1: the pilot has no artificial deadline

The pilot can last several months at no additional cost, and modules can be tested in parallel on the same instance. That is why the parallel period does not have to be squeezed into a few days. Take the decision to stop paper according to criteria, not the calendar.

Hours of paper work depending on the length of the period

Hours of paper work depending on the length of the periodBar chart: 30 hours at 20 days, 60 at 40 days, 90 at 60 days.020406080100h20 days: 30 h30 h20 days40 days: 60 h60 h40 days60 days: 90 h90 h60 days
Source: Example calculation: 6 people x 15 min per day x number of days

Recommendation 2: set the criteria for stopping paper

The criteria should be numerical and verifiable. Examples: all permits in the chosen area issued in the system over two full shift cycles, no discrepancies between paper and system in the last week, every person entering the site has valid training in the system.

Elapsed time alone is not a criterion. The parallel period ends when conformity has been shown, not when the agreed month has passed.

  • two full shift cycles without discrepancies,
  • complete training records for people entering the site in the system,
  • permits in a given area issued only in the system,
  • a named person responsible for signing the decision to stop paper.

Recommendation 3: appoint one owner of discrepancies

When paper and the system say different things, someone must decide which source is true. Appoint one person or role, for example the BHP manager or the implementation coordinator, and set the rule: during the parallel period the system is the source of truth, and paper serves for comparison. Record every discrepancy with its cause.

Without an owner, discrepancies turn into disputes between departments. With an owner they become material for improving the configuration.

Recommendation 4: limit the parallel period to selected areas

You do not have to keep paper everywhere at once. Choose one area, for example one hall or one type of permit, and demonstrate conformity there. Keep paper in the other areas as before, and extend the scope after success. This approach limits the cost of running in parallel and shows the team the benefit faster.

Permit templates, their tasks and scope are configured in the installation data, without changes to the code, so extending an area is usually configuration work, not implementation work.

Recommendation 5: calculate the cost of the parallel period with its assumptions

The parallel period costs people's time. In an example calculation: 6 permit issuers, each keeping paper for an extra 15 minutes a day, over a period of 40 working days. This gives 6 x 15 min x 40 = 3600 minutes, that is 60 hours. This cost should be compared with the risk of gaps in documentation if paper is stopped too early.

Example calculation

Cost of time in the parallel period

Assumptions
ParameterValue
Number of permit issuers6 people
Extra time for paper15 min/day
Length of the period40 working days

Result: 6 x 15 min x 40 days = 3600 minutes, that is 60 hours.

Note: Example calculation; the figures are assumed, not taken from a specific plant.

Video

Frequently asked questions

Must the parallel period be limited to 30 days?

No. The pilot can last several months at no extra cost, so the length is set by the criteria of conformity.

Who decides when paper and the system differ?

The person or role named in advance, for example the BHP manager. Working rule: the system is the source of truth, paper serves for comparison.

Do access control or time attendance systems have to be switched off during implementation?

No. InnerWeb works as an independent supplementing system, so the existing systems keep working unchanged.

Let's set the criteria for stopping paper

Together with your BHP team we will define the pilot area and numerical criteria of conformity. Book a talk or a demo.

Let's talk