Why criteria, not a date
A typical plant starts with work orders on paper and in Excel spreadsheets, companies invited by different people, and training validity tracked by hand. The parallel run serves to show that the system reproduces this reality faithfully. A calendar date does not show that.
A pilot can run for several months at no extra cost, and modules can be tested in parallel on the same instance. The director therefore does not have to end the period because of licence cost pressure and can wait until the criteria are met.
First criterion: data quality
The comparison of paper and system entries shows no deviations for a set time. The consistency gates and the independent check of the plant structure gave a zero result, including zero lines outside the wall. Duplicate accounts have been cleaned up, and duplicate control works for invitations and QR code registration.
The criterion also covers permit templates. The printout reproduces the plant's form through the template matrix, and the tasks and scope are configured in the installation data. If the inspector expects the old look, the printout must meet that expectation.
Paper-system deviations over consecutive weeks (example)
Second criterion: presence and work of users
Users enter permits and lists in the system without going back to paper, and external companies are invited through one channel instead of through different people. The director checks that every team that used to write on paper has accounts and can complete its tasks in the system.
InnerWeb works as an independent system that complements the client's existing systems, so switching off paper does not require switching off access control, time-attendance, HR or ERP. Those systems keep working, and the decision concerns only the paper registers.
Evidence for the audit and keeping the paper archive
Before switching off, the plant records a report: who decided, when and on the basis of which check results. Paper registers from the parallel run are not destroyed, but archived in line with the plant's requirements. The report supports meeting audit requirements, because it shows that the transition was verified and not assumed.
Checklist
Video
Frequently asked questions
After how long can I switch off paper?
After the criteria of data quality and user work are met. The parallel run usually lasts 1-3 months in one hall, but there is no fixed deadline.
Does switching off paper also switch off access control and time-attendance?
No. InnerWeb is a complementary system, and the decision concerns only the paper registers.
What happens to the paper registers after the end?
They are archived in line with the plant's requirements, together with the decision report.
When should your plant end paper?
We will agree the switch-off criteria and the decision report with you, and run the parallel period towards meeting them.