OT Network Location System: What to Put in the Request for Quotation

A power plant procurement department that does not write OT requirements into its request will receive quotes that cannot be compared: one vendor sets up cloud servers, another runs everything locally. Below are eight recommendations that require bidders to work locally in the OT network, to sign frames with the buyer's keys, to follow a device trust procedure and to describe the architecture in the PERA model.

12
steps of the device trust procedure for a BLE wristband
Source: company facts card
10 m
required accuracy in the concept for a large site
Source: offer card

Why the request must mention OT

A request for quotation for an employee location system at a power plant reaches vendors who usually sell cloud solutions. If the buyer does not state that the system must run locally in the OT network, the quotes will come back in two different architectures, and the price comparison will be illusory.

The recommendations below concern procurement in the energy sector and rest on requirements that buyers in this sector have actually set. The division of responsibility for compliance with regulations stays with the buyer: the system supports meeting the requirements and provides evidence, it does not guarantee compliance.

Recommendation 1: local operation without a connection to the manufacturer

A buyer from the energy sector may require the system to operate locally in the OT network without a connection to the manufacturer. Write it in one sentence: the system works in full scope without outbound traffic to the manufacturer and without remote service access outside an agreed procedure.

Reasoning: outbound traffic from the application host is sometimes blocked entirely in the OT network. When that is the case, alarm webhooks are stored in a durable queue, and an external poller picks them up over an inbound channel, so the alarm is not lost without opening outbound traffic. Ask bidders how they solve this.

Indicative cost of a wristband in the concept for a large site

Indicative cost of a wristband in the concept for a large siteHorizontal bar chart: about 500 PLN one-off and about 5 PLN monthly per wristband0100200300400500PLNOne-off per wristbandOne-off per wristband: 500 PLN500Monthly per wristbandMonthly per wristband: 5 PLN5
Source: Indicative ranges from 2025-2026 rollouts; individual estimate

Recommendation 2: frames signed with the buyer's keys

Ask for device frames signed with the buyer's keys, not the manufacturer's keys. The keys are then owned by the operator, and the operator decides on their rotation.

Reasoning: questions from a critical infrastructure operator about a wristband concern not only the origin of the electronics, but also who holds the keys to the firmware. An answer in the request eliminates bidders who will not hand them over.

Recommendation 3: device trust procedure

Require a described device trust procedure: X-ray inspection of samples, control of firmware and keys. For a BLE wristband at a critical site the procedure counts 12 steps and answers supply chain risks: unintended functionality, unauthorized firmware and batches that do not match the sample.

Reasoning: without such a requirement the vendor will declare hardware compliance on paper, and every further batch of wristbands will be a purchase on trust.

Recommendation 4: architecture description in the PERA model

Ask for a diagram in the PERA model, levels 0-6 with DMZ 3.5. Require: an OT network separated by firewalls, no hosts with interfaces in two levels, separate VLANs for management, backup and monitoring, logs to SIEM, VPN access with 2FA and a jump host in the OT DMZ.

Reasoning: the same diagram is read by the IT department, the automation department and the auditor. A bidder who cannot draw it before the quote cannot implement it after the quote.

Recommendation 5: resilience to no daily charging

A wristband charged once a year is a different operating cost than a card charged daily. Write in the required charging interval, the alarm for removal or cutting of the strap and the SOS button.

In the concept for a large energy site the BLE wristband only transmitted, the required accuracy was 10 m, and data left only through the main antennas to the OT VLAN and to servers in the OT network. These parameters organize the comparison of offers.

Recommendation 6: where the servers are

Ask where the servers run: at the buyer's site, in the OT network. The operator also asks about the origin of the electronics. Combining these two questions with the requirement for local operation closes the topic of dependence on the manufacturer.

Recommendation 7: scope of the estimate

Split every offer into the same items: site visit, BLE propagation measurements, placement design per floor, integration with OT, system adjustment, training. An estimate built this way for a concept for a large energy site gave, when divided per wristband, a figure of the order of 500 PLN one-off and about 5 PLN per month. These are indicative ranges from 2025-2026 rollouts; the individual estimate is separate.

Reasoning: a uniform scope lets you compare the offers, not their assumptions.

Video

Frequently asked questions

Can the location system work without a connection to the manufacturer?

Yes, a buyer from the energy sector may require it. The system works locally in the OT network, and when outbound traffic is blocked, alarms are stored in a queue collected over an inbound channel.

What does the device trust procedure cover?

12 steps, including X-ray inspection of samples and control of firmware and keys. It answers the risks of unintended functionality, unauthorized firmware and batches that do not match the sample.

Why put the PERA model into the request?

It gives IT, automation and the auditor a common language. The bidder draws the architecture before the quote, so differences in assumptions come out immediately.