Risk Assessment Before and After Preventive Measures

A risk assessment in the editor consists of three numbers: probability, exposure and severity, and the level is their product. It is assessed twice, before the preventive measures and after them. Below we explain the thresholds, the default copying of values and the mistakes that spoil the result.

126 to 42
sample level before and after measures
Source: sample calculation

What the risk card contains

The risk card has its name in Polish and English, a description, a pictogram, a list of preventive measures, and an assessment of probability, exposure and severity before and after the measures. There is always one pictogram, with no option to leave it blank. The whole is created in the editor shared with the settings of high-risk work.

The assessment is performed and approved by a person. The editor does not invent it: it calculates the level from the entered values and shows it live as a level marker. The documentation does not describe risk assessment by artificial intelligence, so substantive responsibility remains with the safety team.

How the risk level is calculated

The risk level in the editor is probability times exposure times severity. The result is compared with the thresholds 20, 70, 200 and 400, and the editor shows the level marker live. When you change any of the three values, the marker changes immediately, so you see the effect of your assessment.

Example: probability 3, exposure 6 and severity 7 give 126. This is above the threshold of 70 and below the threshold of 200. After the preventive measures probability falls to 1, and with the other values unchanged the result is 42, which is below the threshold of 70.

  • Before measures: 3 x 6 x 7 = 126
  • After measures: 1 x 6 x 7 = 42
  • Comparison thresholds: 20, 70, 200, 400

Risk level before and after measures (example)

Risk level before and after measures (example)Risk level falls from 126 to 42 after lowering probability from 3 to 1050100150levelBefore measures: Level: 126 level126 levelBefore measuresAfter measures: Level: 42 level42 levelAfter measures
Source: Sample calculation: 3 x 6 x 7 and 1 x 6 x 7

Why exposure and severity are copied over

After the preventive measures exposure and severity usually remain unchanged, and probability falls. That is why the editor copies exposure and severity from the assessment before the measures by default. It stops doing so once the user changes the field by hand.

This protects against a common mistake: the assessor changes the probability after the measures, and exposure and severity accidentally drift apart between the two assessments. Default copying keeps both assessments on the same scale. If a change of exposure is justified, for example thanks to a barrier limiting the time spent in the area, you enter it by hand and the editor respects it.

Step-by-step assessment procedure

Start with the assessment before the measures: establish how likely the event is, how often people are exposed, and what the consequence would be in the worst realistic scenario. Enter the preventive measures, and only then enter the assessment after the measures.

Make sure the justification for a change is described in the measures: who does what and when, so that the probability falls. A result after the measures without described measures is a number you could not defend in front of an auditor.

  • Assess probability, exposure and severity before the measures
  • Enter the specific preventive measures
  • Assess probability after the measures, leaving exposure and severity at their default
  • Change exposure or severity by hand only with a justification
  • Check the level marker against the thresholds 20, 70, 200 and 400

Pitfalls and proof for the audit

The most common pitfall is an assessment after the measures that is lower only because the measures are in the plan, not implemented. The risk card shows the assessment, but the plant is responsible for implementing the measures. A second pitfall is editing a risk without knowing that it is global: the change applies everywhere the risk is used.

For the auditor the value lies in a well-organised card: name, description, pictogram, measures, assessment before and after, and the level. The system provides proof for the audit, while the substantive assessment remains with the plant.

Video

Frequently asked questions

Does the editor propose assessments by itself?

No. The editor calculates the level from the entered values and shows it as a marker. The assessment is performed and approved by a person.

Why is exposure after the measures the same as before?

Measures usually reduce probability, while exposure and severity stay the same. The editor copies these values by default until you change them by hand.

What are the thresholds of the risk level?

The level, which is the product of the three assessments, is compared with the thresholds 20, 70, 200 and 400.

Does a change of assessment apply to only one place?

No. The risk is an element of the global catalogue, so a change applies everywhere the risk is used.