Hot work: eight permit states from request to closure

Hot work in the digital permit passes through eight states: from the request, through the knowledge check and approval, to opening, observation and closure. Each transition has a rule that says who may carry it out and when. This guide walks through the states in turn, so the coordinator knows what the system will allow and what it will block.

8
states of a permit for especially hazardous work
Source: spec sheet
3 h
minimum observation time before closing hot work
Source: spec sheet

Why hot work needs its own state machine

A permit for especially hazardous work (PSZN) is in the system a separate state machine with eight states. It cannot be opened or closed without the next steps: the rules are written into the code, so they do not depend on the coordinator's memory or on whether someone skipped a form field.

What sets hot work apart is that the hazard does not disappear when the work ends: embers can smoulder for hours. That is why, in this type of work, observation after the works is built into the flow and cannot be skipped.

States 1-3: request, knowledge check, decision

The first state is the request: the application is created in the system. The second is the knowledge check: before the decision, it is confirmed that the contractor knows the risks. The third is the decision, which ends in approval or rejection.

Only a user on the plant's side may approve or reject a PSZN, not the external contractor. This safeguard separates the roles: the person who is to carry out the work cannot authorise it themselves. Rejection is a final state: the application returns for correction as a new one.

Observation windows after hot work

Observation windows after hot workHorizontal bar chart: observation window I lasts 1 hour, window II 4 hours, the minimum observation before closure is 3 hours.01234hoursObservation window IObservation window I: 1 hours1Observation window IIObservation window II: 4 hours4Minimum observation beforeclosureMinimum observation before closure: 3 hours3
Source: Spec sheet of the permit function for especially hazardous work: 1 h and 4 h windows, closure blocked until at least 3 h

States 4-5: opening and the start of works

After approval the work can be opened. Opening is the moment from which the working time is counted and from which the system knows that the hazard is on site.

For hot work, opening is not the last step but the entry into a phase after which observation follows. The coordinator sees that the permit is open and that, after the works, it must not be closed straight away.

States 6-7: observation in the 1-hour and 4-hour windows

After hot work is opened, observation follows in a 1-hour window, and then in a 4-hour window. The move to the second window is possible only after the first hour has passed. Closure is blocked until at least 3 hours of observation have passed.

The observation is carried out by an external fire watch, not by a plant employee. The coordinator therefore cannot enter the observation on the contractor's behalf: the system assigns this step to the person who actually watches the place after the works.

  • 1-hour window: first observation after the work is opened
  • 4-hour window: possible after the first hour has passed
  • closure blocked until at least 3 hours of observation have passed
  • observation is carried out by an external fire watch

State 8: closure and the last-worker rule

The eighth state is closure. A PSZN cannot be closed while more than one worker remains on site. The rule prevents the permit from being closed while part of the crew is still at the workplace.

For hot work, the above rule is joined by a time lock after observation. For other types of hazardous work, which do not require observation, closure is possible earlier, once the last worker has left the place.

The permit and PSZN are two independent modes

This is a business decision the coordinator should know: the PSZN and the permit status are two independent modes. Open PSZN tasks do not block the permit from moving from preparation to the main works or to completion.

Once the permit has started, open PSZN tasks move from the preparation column to the main works column, where they are confirmed by the contractor or the administrator. It has happened that the permit card showed 'Preparation 0/0': the cause was a template item skipped by the wizard, not this rule, so the wizard was corrected.

Checklist

Video

Frequently asked questions

Who may approve a hot work permit?

Only a user on the plant's side. The external contractor may neither approve nor reject their own application.

How long does observation after hot work last?

Observation passes through a 1-hour window and a 4-hour window, and closure is blocked until at least 3 hours of observation have passed.

Can a plant employee carry out the observation?

No. The observation is carried out by an external contractor acting as the fire watch.

Do open PSZN tasks block the permit?

No. The PSZN and the permit status are two independent modes; open PSZN tasks do not block the permit from moving on.