Preparation 0/0 on a permit: a wizard case

After several permits for especially hazardous work were approved, the card showed "Preparation 0/0". The administrator asked whether the system was blocking the preparation tasks. The cause turned out to be the wizard, not a system rule. This case explains how to tell the two apart.

8
states of the PSZN state machine, from request to closing
Source: feature card
5
risk sections on the permit printout
Source: feature card

Symptom: zero preparation tasks after approval

In a real case, after several permits were approved, the permit card showed "Preparation 0/0". For the person issuing the permit, this was a sign that the list of preparatory actions was empty, even though the work belongs to the category of especially hazardous work, for which such actions should exist.

The first reflex in such a situation is to look for the fault in the rules: perhaps the system deliberately hides the tasks, or something blocks the permit from moving on. This reflex should be held back, because it leads to changing settings that were working correctly.

Two modes that are easy to confuse

The first fact to establish: in the system, the permit for especially hazardous work is a separate state machine with eight states, from the request through the knowledge check and approval, to opening, observation and closing. The status of the permit itself is a different mechanism.

The business decision is unambiguous: PSZN and the permit status are two independent modes. Open PSZN tasks do not block the permit from moving from preparation to the main work or to closing. Once the permit is started, open PSZN tasks move from the preparation column to the main work column, where they are confirmed by the contractor or the administrator.

  • zero tasks in preparation does not necessarily mean a block,
  • PSZN tasks can appear in the main work column,
  • the independence of the two modes is the rule, not a fault.

Diagnosis: a rule or the wizard

When the card shows 0/0, the administrator answers three questions in turn. Is a template assigned to the permit at all? Do the PSZN tasks exist but sit in a different column? Did the wizard save all the elements of the permit when the hazardous work was selected?

In the case described, the answer was yes to the first question: the wizard skipped the permit template when PSZN was selected. Without the template, there was nothing from which the preparation tasks could be generated. The cause was not the rule of mode independence; the fix concerned the wizard.

A quick test that separates a fault from a rule

It is enough to compare two permits created from the same template: one created with PSZN selected, and one without. If only the first shows 0/0, the problem lies in the wizard. If both have preparation tasks and the PSZN tasks sit in the main work column, the system works according to the rule.

What follows for issuers and the administrator

For the issuer: a 0/0 view after selecting PSZN is a reason to report the problem, not to work around it manually. For the administrator: before changing the rules, the wizard should be checked, because changing the independence rule would break a behaviour that was designed on purpose.

A safety principle also applies: only a user on the plant side can accept or reject PSZN, not an external contractor. A wizard error does not change this principle and should not lead to handing over permissions as a workaround.

Risks on the printout: what to check after the fix

After the wizard is repaired, check the printout of the permit. It lists the risks in five sections: risks common to the permit, the location hierarchy, additional locations, the type of hazardous work and the user risks. Each risk is shown only once, so the check is short.

If a risk is missing, the health and safety officer or the administrator can add it in the shared editor. From that moment the risk is available for selection by all issuers of permits.

Video

Frequently asked questions

Does 0/0 mean the permit is blocked?

No. Open PSZN tasks do not block the permit from moving from preparation to the main work. In the case described, the 0/0 result came from a wizard error.

Who can accept PSZN?

Only a user on the plant side. An external contractor does not accept or reject such work.

Where do PSZN tasks go once the permit is started?

To the main work column, where they are confirmed by the contractor or the administrator.

How do I add a missing risk?

The health and safety officer or the administrator adds it in the shared editor. The risk is then available to all issuers of permits.