Checklist for handover of a service firm during a bag filter overhaul

Overhauling a baghouse dust collector filter means working with combustible dust, often with tools that produce sparks, so the plant coordinator's handover of the work to an external company has several mandatory points. This checklist organises them into three stages: before the work, during the work and after the work, with a comment on each.

1 h i 4 h
monitoring stages after work with fire
Source: feature card
3 h
minimum monitoring before closing the work
Source: feature card

How to use this checklist

The checklist is intended for the coordinator on the plant side, who hands the workstation over to the external company and takes it back after the work. It does not replace the permit or the plant's instructions; it only organises what needs to be checked.

The points assume that the work is run in the permit system and that, if fire is used, monitoring after the work applies. Before applying them, compare them with your own instruction on hot work.

Before the work

At this stage it is decided whether the work may start at all. A permit for work with fire is work classified as particularly hazardous; it is a separate object attached to the permit with its own state machine, and only a user on the plant side can approve or reject it.

The coordinator confirms the scope: which filter, which bags, which tools, whether the dust collector has been disconnected and cleaned of deposits. The description of the work should be specific enough to tell when the work has gone beyond its scope.

Monitoring after work with fire

Monitoring after work with fireBar chart: first monitoring stage 1 hour, second stage 4 hours, minimum monitoring before closing 3 hours.01234hFirst stage: 1 h1 hFirst stageSecond stage: 4 h4 hSecond stageMinimum before closing: 3 h3 hMinimum before closing
Source: Feature card: monitoring after work with fire

During the work

During the work the coordinator does not have to stand next to the filter, but must be able to react. A plant user can suspend an active permit. The suspension blocks closing tasks other than the unblocking tasks indicated by the person who suspended it, so if unexpected dust build-up appears, the crew may carry out only the securing actions.

The permit flow for work ordered from an external company runs on a single permit, so the coordinator sees the same data as the contractor and does not have to ask about the status.

After the work: monitoring and handover

The stage most often skipped is monitoring after the work. For work involving fire the system enforces a monitoring period after completion in two stages, 1 h and 4 h, carried out by a fire watch on the contractor side. Closing the work is blocked until at least 3 hours of monitoring have elapsed.

Only after this does the coordinator take back the workstation: checks that the filter is closed, that residual materials have been removed, that no smouldering deposits remain and that the permit has been closed in the system.

Checklist

Video

Frequently asked questions

Who carries out the monitoring after work with fire?

The fire watch on the contractor side, in two stages: 1 h and 4 h. The plant coordinator takes back the workstation after the monitoring is complete.

Can the work be closed before 3 hours have passed?

No. Closing work with fire is blocked until at least 3 hours of monitoring have elapsed.

What to do if unexpected dust build-up appears during the work?

Suspend the permit. Suspension allows only the tasks on the unblocking list indicated by the person who suspended it to be closed.