What makes up downtime during service
Downtime during a printing press service is the sum of three segments: waiting for the technician to be admitted, preparing the station, and the actual repair. Only the third segment is time paid to the technician. The first two are time when the press stands still and nothing happens except preparation.
Production management sees this differently from maintenance. For production, an order is standing still; for maintenance, preparation is in progress. A good calculation does not look for someone to blame. It breaks the hours into segments and shows which of them can be shortened without changing the repair itself.
- Waiting: approval of the permit and verification of the technician's qualifications.
- Preparation: isolating the power supply, securing the station, taking the machine over from the operator.
- Repair: the actual service work, which the organisation cannot shorten.
What changes when the permit is ready before the technician arrives
In the system, a permit without preparation tasks goes straight to the main work after approval, while one with preparation tasks first goes to the in-preparation status. This distinction matters for the calculation: when preparation tasks, for example isolating the power supply, are done by the plant's staff before the technician reaches the hall, the technician starts with the actual work after entering.
The change does not shorten the repair; it moves the preparation before the arrival. The permit is approved earlier, the preparation tasks are ticked off, and when the technician enters, the downtime hour is already used for work.
What suspending a permit with a downtime cost does
An internal user can suspend an active permit when the contractor has done something that needs correcting, and the suspension blocks closing all tasks except the list of unblocking tasks. The suspension does not stop the permit clock: the term keeps running, and after the resumption the permit may be past its term and require a separate extension. In the cost calculation it is therefore worth counting the suspension hours as a loss, not as neutral time.
Downtime hours per service (sample calculation)
- Without an early permit
- Permit ready before arrival
Sample calculation: assumptions and result
The assumptions below are illustrative and serve to show the method of calculation. Replace them with your own: the cost of an hour of downtime from controlling, the number of services from the maintenance plan, and the number of preparation hours that can be moved before the arrival.
With the assumptions from the calculation box, we recover 12 hours per month, which at 1,200 PLN per hour of downtime gives 14,400 PLN. The calculation does not include the cost of the system, because pricing is individual and depends on the number of modules, sites and the scope of implementation.
How to check the assumptions on your own data
The sample calculation is turned into your own figure in three steps. The first is collecting from the last quarter the times from the report of a failure to the technician's entry into the hall, and from entry to the start of the actual repair. The second is separating the hours that depend on the technician's availability from those that depend on the plant, that is, on approval and preparation of the station.
The third step is assessing how many of the plant's hours can be moved before the arrival. In most plants this is between half and two thirds, but only your own measurement gives a number that can be entered into the investment plan. Indicative ranges from 2025 to 2026 implementations should be compared with an individual quote for such a calculation.
- Collect 5 to 10 services from the last quarter with the time of each segment.
- Separate the time that depends on the technician from the time that depends on the plant.
- Estimate how many preparation hours can be done before the arrival.
- Multiply by the cost of an hour of downtime from controlling, not by an industry average.
What this calculation does not cover
The calculation does not cover quality costs, such as scrap after the machine is restarted, or contractual penalties for a delayed order. It also does not include the gain from better shift organisation, because that depends on local arrangements.
InnerWeb is a software producer, so we do not promise a specific number of hours. We provide a tool that allows the preparation to be moved before the arrival and that proves in an audit that the permit was ready and the decision to enter the hall was taken in good time.
Recovered Downtime Hours in Printing Press Service
| Parameter | Value |
|---|---|
| Printing press services | 6 services per month |
| Hours recovered per service | 2 h |
| Cost of an hour of machine downtime | 1,200 PLN (sample assumption) |
Result: 6 services x 2 hours = 12 hours recovered per month; 12 x 1,200 PLN = 14,400 PLN per month, or 172,800 PLN per year, before the cost of the system.
Note: Sample calculation based on assumptions stated in the table; replace the values with your own data from controlling and the maintenance plan. The system is priced individually.
Video
Frequently asked questions
Does a permit ready before the technician arrives shorten the repair itself?
No. It shortens the waiting and preparation segments, which depend on the plant. The duration of the actual repair depends on the fault and the technician.
Why is a permit suspension counted as a loss in the calculation?
Because the permit clock keeps running during the suspension, and after resumption the permit may be past its term and require an extension.
How do I put in my own cost of an hour of downtime?
Take it from the plant's controlling, including the margin on the order and the fixed costs of the line. An industry average is not suitable for an investment plan.
Let us calculate the downtime on your figures
We will go through your last 5 to 10 services together, break the hours into segments and show how many of them can be moved before the technician arrives.