Cost of approver duty during the peak hours of permits

At a continuously running plant, 82% of permits fall between 6:00 and 10:00 a.m., mostly on Tuesday and Wednesday. An approver on duty in that window is 4 hours a day, and with two peak days a week that means 8 hours of double staffing. Below is a sample calculation that the safety department can convert into its own rates.

82%
of permits issued between 6:00 and 10:00 a.m.
Source: analysis of 106 permits over 9 weeks at a continuously running plant
8 h
of double staffing a week with two peak days
Source: sample calculation

Permit distribution: why the peak costs money

An analysis of 106 permits collected over 9 weeks at an insulation materials plant running continuously shows decisions bunched together in time. 82% of permits were issued between 6:00 and 10:00 a.m., and 62 of 106 on Tuesday and Wednesday. None were issued at the weekend.

Bunching means the approver staffing has to match the peak, not the average. If approvals were spread evenly across the week, one approver would be enough. If they stay as they are, the four-hour window may run short of hands, and contractors wait at the gate for a decision.

Structure of the duty cost

The cost of duty consists of the approver hours in the peak window, the hours of a second person on the days of greatest load, and the cost of contractors waiting. The first two components can be counted exactly, while the third requires an assumption about the external company's rate.

Basic staffing hours

The window from 6:00 to 10:00 is 4 hours a day. Over five working days this gives 20 hours of basic staffing in the week, if the plant staffs the window on every working day.

Double staffing hours

Sample calculation: a duty of approvers in the 6:00 to 10:00 window is 4 hours a day, and 2 peak days a week give 8 hours of double staffing. This is an assumption for your own costing, not the result of an implementation.

Permits by time of issue

Permits by time of issueDonut chart: 82 percent of permits between 6:00 and 10:00 a.m., 18 percent at other hoursBetween 6:00 and 10:00 a.m.: 82 percent (82%)Other hours: 18 percent (18%)100percentBetween 6:00 and 10:00 a.m.82 percent (82%)Other hours18 percent (18%)
Source: Analysis of 106 permits over 9 weeks; other hours = 100 minus 82

Sample weekly calculation

With the assumptions in the table below, basic staffing is 20 hours a week, and double staffing on peak days adds 8 hours. Together that is 28 hours of approver staffing in the week, of which 8 hours concern Tuesday and Wednesday only.

The value in currency depends on the hourly rate of the approver in your plant. That is why we give hours, and leave the conversion into money to the finance department. A plant with a different distribution of permits should replace the 4 hours with its own window.

How to lower the cost without losing control

The simplest way is to level the peak by submitting requests earlier. If a contractor submits a request a day in advance, the decision does not have to be made between 6:00 and 10:00 a.m. The second way is to reduce general locations: a precise point at the machine shortens the decision time, because the approver does not need to ask where the work is.

In the analysis, 44 of 106 permits pointed to a general location. If the share of these permits falls, every decision in the peak will be shorter, and the same staffing will handle more permits. The indicator of general locations is described in a separate guide.

Approver staffing hours per week

Approver staffing hours per weekBar chart: 20 hours of basic staffing, 8 hours of double staffing, 28 hours in total per week0102030hoursBasic (5 days at 4 h): 20 hours20 hoursBasic (5 days at 4 h)Double (2 days at 4 h): 8 hours8 hoursDouble (2 days at 4 h)Total: 28 hours28 hoursTotal
Source: Sample calculation based on the assumptions in the calculation section

Where the permits to approve are concentrated

In the same analysis, 43 permits covered hot work, 40 covered work at height, and 76 of 106 permits concerned two halls. In the warehouse hall 24 of 39 permits concerned work at height, and in the production hall 24 of 37 were hot work. The duty can therefore be set up for specific halls and types of work, not for the whole plant.

The four largest contracting firms held 63% of the permits. It is worth agreeing a fixed window for submitting requests with them, because that is the cheapest way to level the peak.

Example calculation

Sample calculation: approver staffing per week

Assumptions
ParameterValue
Peak window6:00 to 10:00 4 hours a day
Working days with duty5 days a week
Peak days with double staffing2 days a week

Result: 5 times 4 hours is 20 hours of basic staffing, 2 times 4 hours is 8 hours of double staffing, 28 hours a week in total.

Note: Sample calculation: the assumptions serve your own costing and are not the result of an implementation. The hourly rate is set by the plant.

Video

Frequently asked questions

Is duty needed at the weekend?

The analysis shows no permits issued at the weekend, so weekend duty did not follow from the data. A plant with a different shutdown schedule should check its own distribution.

How do I know that the peak is Tuesday and Wednesday?

From the analysis of 106 permits over 9 weeks: 62 fell on those two days. The plant will read its own distribution from the list of permits over several weeks.

Can a second approver be replaced by a system rule?

Only the user on the plant side approves or rejects a permit, so the second approver can be replaced only by another plant user, not by a rule for the contractor.

How do I convert hours into cost?

Multiply the 28 hours a week by the approver's hourly rate and by the number of weeks of the shutdown or the year. The rate is internal data of the plant.

Calculate the staffing for your peak