Work permit green card: concept for the plant

At a machine manufacturing plant, a contractor's foreman joins the permit team and sees on his phone that he is "in work". Can he start? Not always, because joining the team is not the same as being cleared. Below is the concept of a permit consent card that separates these two states by color and message, based on an InnerWeb function rather than a description of a deployment.

2
card states: amber and green
Source: card
8 people
example crew in the calculation
Source: sample calculation

The problem: two different states, one phrase "I am in work"

In a permit for hazardous work, the contractor goes through several stages. First the permit is prepared: the scope, risks, protective measures and team are set. Only after the preparatory tasks are done does the plant-side authorizing person issue the instruction to start work. A contractor who joined the team at an earlier stage therefore sees the permit with his name in the app, but does not yet have consent to start.

In practice at production plants this difference gets lost. The crew sees their names on the list, someone says "we are listed", and some people take it as consent. For the head of a department this is a classic risk: work started before formal clearance, without confirmed protective measures.

The consent card concept answers the question from the draft: how to show on the foreman's phone, at a glance, which of the two states his team is in. The contractor's foreman's job is then to read the color and the message, not to interpret the terminology of a form.

Two cards: green and amber

The permit card on the external company's screen is green, with the words "CONSENT TO PERFORM WORK", and only after clearance for the main or closing works. This is a hard condition: without clearance there is no green card, regardless of who is in the team or which tasks have been ticked off.

A worker who joined the team while the permit is in preparation sees an amber card with the message "You have joined the work - confirm the preparatory tasks". Amber is the color of waiting: you are in the team, you have something to do, you cannot start yet. The message leaves no room for guesswork, because it names the next step.

This split works well on the shop floor, where the phone is used with gloves and in noise. The color is visible from arm's length, and the text message confirms it for people who do not distinguish colors. The plant can also show the same thing on a screen at the work station for the whole crew.

  • Green card: "CONSENT TO PERFORM WORK", only after clearance for the main or closing works.
  • Amber card: "You have joined the work - confirm the preparatory tasks", while the permit is in preparation.
  • No green card means no consent, even if the contractor is listed in the team.

Example crew of 8 people: number of cards in each color

Example crew of 8 people: number of cards in each colorBefore clearance 8 amber cards and 0 green, after clearance 0 amber and 8 green.02468peopleAmber card (After joining): 8 people8 peopleGreen card (After joining): 0 people0 peopleAfter joiningAmber card (After clearance): 0 people0 peopleGreen card (After clearance): 8 people8 peopleAfter clearance
  • Amber card
  • Green card
Source: Sample calculation: a crew of 8 people, all join before clearance

What the card does not do: the limit of responsibility

The contractor's card does not replace the instruction to start work issued by the authorizing person. This rule must be communicated to the teams already during the induction. The green color reflects the human decision, it is not its source. Clearance still requires a conversation, an inspection of the workstation and signing in the system by an authorized person.

Why does this matter? Because a color on a phone is sometimes misread as self-granted consent. If someone sees green in the wrong place, for example in a screenshot taken earlier, they may think they have permission. That is why the card refreshes from the system, and the plant procedure should state clearly: we enter the work after an instruction from the authorizing person and after reading the current card.

For the OHS department this is also an audit argument. Separating the state "in the team" from the state "cleared" shows that the plant has introduced a barrier against premature start, rather than merely writing the rule into an instruction.

Demo scenario: the contractor's foreman at a machine plant

Imagine an agricultural machinery plant owned by a global group, where an external service crew has to replace an installation element above the assembly line. The contractor's foreman receives the permit invitation and joins the team from his phone. He immediately sees the amber card with the message about the preparatory tasks.

The crew confirms the preparatory tasks: marking the zone, isolating the power supply, checking the equipment. After these steps the authorizing person from the plant comes to the workstation, checks it and clears the team for the main works. At that moment the card for each team member changes to green with the words "CONSENT TO PERFORM WORK".

This is the value of the demo for the plant management: there is no need to explain the procedure with slides. It is enough to show two phones side by side, one with the amber card and one with the green, and ask who may start on which of them. We describe this as a concept: the plant should check it on its own permit templates and its own list of roles.

What to set up before launching the card

First, the role of the authorizing person. The card changes color only after clearance, so the plant must have clearly defined who clears the main and closing works, and must have a person for each shift who can do it. Without this, amber stays amber for half a shift.

Second, the preparatory tasks. The more meaningful they are, the more the confirmation by the contractor means. A list of a dozen items ticked out of habit works as an empty formality, while five concrete tasks linked to the permit risks have a real effect.

Third, communication to the contractors. One page of instructions with two screenshots of the cards, handed out together with the badge and discussed during the induction, removes most misunderstandings. It is worth adding a sentence that the green card does not replace the instruction from the authorizing person.

Effect: what changes in the behavior of the crews

In an example crew of 8 people, everyone sees the amber card after joining. After clearance, all 8 see the green card. The numbers are illustrative, but they show the essence: the status of the team is unambiguous and the same for everyone who has a phone in hand, and the foreman does not have to ask each person separately whether they may start yet.

For the plant the benefit is twofold. The risk of a premature start decreases, and every clearance decision is recorded in the system with the time and the person. For the contractor the benefit is a shorter downtime: since the green card appears immediately after clearance, the crew does not wait for a phone call saying they can enter.

Video

Frequently asked questions

Is the green card enough to start work?

No. The card reflects the clearance, but does not replace the instruction to start work issued by the authorizing person.

When is the card amber?

When the worker has joined the team while the permit is in preparation and still has preparatory tasks to confirm.

Who sees the green card?

External company workers in the permit team, after clearance for the main or closing works.

Is this a description of a deployment?

No. It is a concept for a plant of the machine manufacturing type, based on a system function, to be checked against the plant's own templates.