Checklist for launching invitations and visits at the plant

Before the production start of the invitations and visits module the implementation project manager should close a dozen or so points: from the delivery channel, through training and the No password status, to the QR poster and hosts. This list orders the acceptance and indicates which evidence is worth keeping.

7 days
validity of the activation link
Source: system feature
89
maximum number of items on the host list in the planning window
Source: system feature

How to use this list

The list serves as an acceptance protocol. Each point has a responsible person and evidence: a screenshot, a test result or a record in the system. An acceptance without evidence is a hypothesis, not a closed point.

The order follows the path of the guest: first the invitation and the account, then the training, then entry and the visit, and finally settlement and support. In this way errors show up where they arise.

Invitations and accounts

Check the delivery channel: email comes first, an SMS with a short link is the backup, and without either of them the operator receives the link to pass on in person. The account may exist despite an undelivered email, so the support team must be able to read the delivery channel.

Verify that the activation link is valid for 7 days and can be opened repeatedly until it expires, and that an expired link leads to login with a message, not to a 404 error. Also check that an account from an invitation activates after the password is set, while an account from self-registration waits for approval from a person with authority.

Acceptance points by stage of the guest's path

Acceptance points by stage of the guest's pathDonut chart: 3 points on invitations, 3 on training, 4 on the QR poster and visits, 3 on scale and support.Invitations and accounts: 3 points (23.1%)Training and password: 3 points (23.1%)QR poster, kiosk, visits: 4 points (30.8%)Scale and support: 3 points (23.1%)13pointsInvitations and accounts3 points (23.1%)Training and password3 points (23.1%)QR poster, kiosk, visits4 points (30.8%)Scale and support3 points (23.1%)
Source: Breakdown of the checklist points on this page

Training, password and entry

Make sure the introductory training is active in every language in which accounts will be created. If there is no active training in the account's language, the person goes straight to the password. Training material should not depend on an external video service, which may hang behind the plant firewall without an error message.

Check the behaviour of the passwordless account: a guest who has completed the training is admitted like an active account, and on the lists has the status No password. Also verify that after the password is set the user is logged in automatically, and that with 2FA enabled they return to the login form.

QR poster, kiosk and visits

Test registration from the QR poster: a visit is created for today, and the guest chooses the host. Check the kiosk: a trained person is welcomed, an untrained one receives the training. In plants with hygiene requirements also check the health declaration, which applies to guests and external companies and exempts internal employees.

Test the scheduled visit: a visit removes only the work permit requirement, while training and the account still decide on entry. Check the call to the host: one at the first entry, and a group call after 30 seconds of silence for further guests of the same host within 3 minutes.

Scale and support

For mass invitations remember that there is no bulk import: onboarding is a loop of creating an account and sending an invitation, roughly 2 seconds per account. Plan the division into batches and a time window.

Hand over the diagnostic instruction to the help desk and confirm who schedules visits: administrator, manager, health and safety, and security on the day of arrival. The coordinator of an external company does not schedule visits. The rollout pattern of a corrugated packaging manufacturer and the concept for an agricultural machinery plant show that the same points apply in different environments.

Checklist

Video

Frequently asked questions

Who should sign the acceptance of the module?

The implementation project manager together with representatives of security, HR and IT. Each confirms the points in their area with evidence.

Does testing the QR poster registration require a real guest?

No, a person from the project team is enough. They go through the path by phone and confirm that a visit is created for today with the chosen host.

What is the most common gap before the start?

Missing active training in one of the account languages. The person then goes straight to the password, while the plant expects the training.

Accept the module with evidence

We will go through the acceptance protocol and the tests before the production start with you. Book a conversation with the InnerWeb team.