Injection machine service permit checklist before approval

The approver on the plant side is the last person who can stop hazardous work before a contractor starts servicing an injection machine. The checklist below organises what to check on the permit: authority, qualifications, risks, printout and the risk assessment. Each point has a note on why it matters on an injection plant floor.

5
risk sections to review on the printout
Source: karta
3 h
minimum time before closing hot work
Source: karta

Who approves, and on what basis

Only a user on the plant side can approve or reject hazardous work, not the contractor. The approver should treat this as a decision, not a signature on a form: they have the right to require the tasks to be supplemented, the team to be changed, or the work to be postponed.

Before approving a permit, open the summary and check the expected status calculated on the server, together with the print preview from the plant's matrix. This is the only moment when the whole picture is visible, as the contractor will see it on the floor.

Section 1: team and qualifications

When a permit is created, the system automatically checks whether the assigned workers hold the required, valid qualifications, medical examinations and training. The approver should confirm that no warnings were skipped and that the team fits the type of service.

For hydraulic service different qualifications are required than for servicing the heating system of a barrel, because required qualifications are defined separately for each type and subtype of hazardous work. Check that the correct subtype has been selected.

Risk level thresholds in the assessment

Risk level thresholds in the assessmentFour risk level thresholds: 20, 70, 200 and 400 points.0100200300400pointsThreshold 1Threshold 1: 20 points20Threshold 2Threshold 2: 70 points70Threshold 3Threshold 3: 200 points200Threshold 4Threshold 4: 400 points400
Source: Documentation of the risks and hazardous work functions

Section 2: risks on the printout

Risks on the printout are assembled into five sections with deduplication: risks shared between permits, the hall, area, line and location hierarchy, additional locations, the type of hazardous work, and risks added by the issuer. The approver should review all five and ask whether anything is missing.

In the risk assessment after protective measures, usually only the probability drops, while exposure and severity stay the same. If the assessment after measures looks too optimistic, that is a reason to talk to the issuer, not to approve with reservations.

Section 3: energy isolation and closing the work

For an injection machine service, energy isolation is critical: electrical, hydraulic, pneumatic and thermal. Check that the tasks of the hazardous work cover all sources and that someone is responsible for confirming them when the permit starts.

Remind the contractor of the closing rules: the system does not allow a hazardous work item to be closed while more than one worker remains on site. For hot work, monitoring runs at 1 h and then 4 h, and closing is blocked until at least 3 hours have passed.

What to do when something in the permit raises doubt

Rejection is one of the eight states of hazardous work, so the approver has the right channel for doubts. Tell the issuer what is missing: a task, a risk, a team member's qualification, or a change of date. The issuer corrects the request, and you assess it again.

Good practice is to agree with shift managers which gaps always lead to rejection, for example missing hydraulic isolation for valve service. Then the approver does not have to invent the rule anew for every request.

Recording the decision and the audit trail

Changes to permits, the taxonomy of hazardous work and training results are saved in the audit trail with the author and the time. The approver's decision can therefore be reconstructed during an incident analysis or inspection: who approved, when, and within what scope.

For the plant this is also protection against a dispute with the contractor. When work is rejected, the record shows the reason, and the contractor sees what to correct. The system provides audit evidence, but it does not replace the judgement of the person who approves.

Checklist

Video

Frequently asked questions

Can I approve the permit if part of the team has no valid training?

The system checks qualifications automatically when the permit is created and warns about gaps. The approver should complete the team or postpone the work.

What if a risk is missing from the catalogue?

An administrator or OHS specialist adds it once in the risk editor. After that it is selectable for all issuers.

Does the permit status depend on closing the hazardous work?

No. These are two independent modes, and unclosed hazardous work does not block the permit from moving between phases.