InnerWeb
Skip to main content

Checklist for installing beacons on poles and structures

Beacons are mounted on poles and structures with cable ties or adhesive, without cables and without mains power, so installation day is mainly logistics and documentation of the points. This checklist guides the installation crew and the security manager from preparing the plan, through fixing and Ex zones, to recording in the database and coverage calibration.

approx. 2 days
installation, calibration and training for 120 beacons in 2 visits
Source: card

Before departure: plan, equipment, authorisations

The installation day starts the day before. The crew should have the layout plan with the number of each beacon and its target point, a list of devices with identifiers to tick off, and a full set of fixing materials: cable ties, adhesive, tools and work-at-height equipment if the points are high.

The security manager confirms the site passes, access to the installation points and working hours, and for explosion-hazard zones checks whether the given place is a zone and whether the work procedure for it has been completed. The InnerWeb beacon has a CE declaration and ATEX certification for zones 2 and 22; for zones 1 and 21 the certification is commissioned for the client's installation.

On the installation day: fixing and recording the point

Each beacon is fixed with cable ties or adhesive on a pole or structure, at the point from the plan, and not in the first convenient place. Changing the point without recording it in the database is the most common source of location errors: a beacon hangs by the road, while in the database it has a position inside the warehouse.

After fixing, the crew records which identifier is at which point before moving on to the next one. The record is made immediately, not at the end of the day, because a mistake across 120 points is hard to reconstruct from memory.

We also watch the uniqueness of identifiers. Two physical beacons with an identical major:minor pair are recognised by the system as one, which later shows up as a route jump on the map.

After installation: calibration and documentation

Coverage calibration of the beacons is set up at the start, before the alarms go live, because the accuracy of localisation depends on coverage. The security manager therefore checks on a walk-round whether at the key points the device receives a sufficient number of beacons, and marks the places to be moved.

For 120 beacons the internal estimate is about 2 working days across 2 visits, so calibration and training fit into the second visit. Later software updates are remote and do not require another trip.

Finally, a photo of each point with its number and notes on difficult access go into the documentation, so that at the battery replacement the service crew knows where to look and what it needs.

The most common mistakes on the installation day

The first mistake is installing a beacon in a different place from the plan without recording the change. The position in the database then does not match reality, and routes draw jumps to places where there is no beacon. Every deviation from the plan is noted on the spot next to the beacon number.

The second is mixing up devices with the same identifier. If two beacons from one batch were programmed identically, this has to be caught before installation, because after installation two points several hundred metres apart will be recognised as one beacon, and correcting the position in the database will not remove the error.

The third is omitting a spare beacon from the documentation. If a pair of devices was left at one point, one of them is active and the other dormant, and both must be described in the database so that nobody later removes the spare that may one day start broadcasting.

Checklist

Video

Frequently asked questions

Does a beacon need cables or mains power?

No. It is mounted on poles and structures with cable ties or adhesive, without cables and without mains power.

When is the coverage calibration done?

At the start, before the alarms go live, because the accuracy of localisation depends on coverage. It usually takes place in the second visit.

Can a beacon be installed in an Ex zone?

The InnerWeb beacon has ATEX certification for zones 2 and 22. For zones 1 and 21 the certification is commissioned for the client's installation.

Prepare the day of beacon installation

Book a conversation: we will adapt this list to your plant, its Ex zones and the layout plan.

Let's talk