What battery power means for the budget
The beacon is mounted on poles and structures with cable ties or adhesive, without cables and without mains power. This means no cost of cabling, cable entries and electrical work during installation, but also no permanent power supply, so energy is a consumable resource that has to be replaced.
The card indicates that an industrial battery lasts for several years, within a temperature range from -40 to 60 degrees C. We do not give an exact number of years as a fixed figure: it depends on the transmission settings and working conditions, so in the calculation we take it as an assumption that the maintenance team should confirm with the battery supplier.
For the maintenance department predictability is key. Replacement is a planned event once every few years, not a continuous repair cost.
What the replacement cost is made of
The cost of one replacement round is the sum of three items: the price of the battery, the working time at the beacon, and the organisation of the round, that is travel, access to places at height and preparing the list of devices to be bypassed. Only the first item depends on the battery supplier; the others depend on the plant.
The largest source of variability is access. Beacons mounted on poles require a lift or a ladder, which lengthens the time of a single replacement. That is why, when designing the layout, it is worth recording at once which points are hard to service.
- Battery price: depends on the type and supplier.
- Time at the beacon: opening, replacement, signal check.
- Round organisation: travel, lift, site passes, bypass list.
Cost of one battery replacement round for 120 beacons
Assumptions of the sample calculation
The calculation covers 120 beacons over a 5-year horizon. All values below are sample assumptions to be replaced with your own; from the card come only the battery operation for several years, the temperature range and the lack of mains power.
- Battery replacement interval: every 4 years (assumption), so 1 round in a 5-year horizon.
- Industrial battery price: 60 PLN per piece (assumption).
- Working time per beacon: 15 minutes, rate 120 PLN per hour, so 30 PLN.
- Round organisation: a crew of 2 people for 8 hours at 120 PLN, so 1,920 PLN.
Result: the cost of a round and the annual cost
One beacon: battery 60 PLN plus labour 30 PLN, total 90 PLN. For 120 pieces this is 10,800 PLN. Adding the round organisation of 1,920 PLN gives 12,720 PLN for a full replacement round across the whole network.
Over the 5-year horizon with one round, this averages 2,544 PLN per year, or about 21 PLN per beacon per year. This is a cost that the maintenance department can plan several years ahead.
Sensitivity to the battery price is moderate. With a battery at 40 PLN the round costs 10,320 PLN, and with a battery at 100 PLN it costs 17,520 PLN. The difference of 7,200 PLN results solely from the unit price, because labour and organisation are kept fixed.
How to reduce the service cost
The cheapest replacement is the one done together with another inspection. If the crew is on site anyway for maintenance of poles or lighting fixtures, the battery round shares the cost of travel and the lift.
The second way is planning by groups. Beacons on one road or in one hall are replaced on one day, which reduces the number of equipment moves. The third is recording in the database which beacons are hard to service, so that at the next round nobody has to search for them blindly.
Remember also the explosion-hazard zones. The beacon has ATEX certification for zones 2 and 22, so battery replacement in such a zone should follow the procedure for that zone, and any certification for zones 1 and 21 is a separate cost.
Battery replacement in 120 beacons, 5-year horizon
| Parameter | Value |
|---|---|
| Number of beacons | 120 pcs |
| Battery replacement interval | 4 years |
| Battery price | 60 PLN per piece |
| Working time per beacon | 15 minutes |
| Labour rate | 120 PLN per hour |
| Round organisation | 1,920 PLN (2 people, 8 hours) |
Result: 12,720 PLN per round (120 times 90 PLN plus 1,920 PLN), on average 2,544 PLN per year over a 5-year horizon, about 21 PLN per beacon per year.
Note: Sample calculation based on the assumptions given above. From the card come only the battery operation for several years and the temperature range; the interval, prices and rates are assumptions to be replaced with your own. Indicative ranges from 2025 to 2026 deployments; individual quotation.
Video
Frequently asked questions
How long does a beacon battery last?
A beacon runs on industrial batteries for several years, within a temperature range from -40 to 60 degrees C. The exact time depends on settings and conditions, so the maintenance team should confirm it on a pilot group of devices.
Does a beacon need a mains power supply?
No. It is installed without cables and without mains power, on poles and structures, with cable ties or adhesive.
What does a battery replacement across the whole network cost?
It depends on the number of devices, the battery price and access. In the sample calculation for 120 beacons it is 12,720 PLN for a full round. These are assumptions, not a price list.
Does replacing a battery in an Ex zone require a separate procedure?
Yes, the replacement is carried out according to the procedure for that zone. The beacon has ATEX certification for zones 2 and 22, and certification for zones 1 and 21 is commissioned for the client's installation.
Plan the service of your beacon network
Book a conversation: we will calculate the life cycle cost of the beacons for your plant, using your rates and your horizon.