Card replacement schedule by shift and gate: guide

Replacing cards in a multi-shift plant must not coincide with the peak of entries, because the queue at the gatehouse holds up the shift. This guide shows how to lay out a schedule of five stages, shifts and gates, so that card issuing falls in low-traffic windows and the old format works until the last wave.

12
cards per hour issued by one workstation at 5 minutes per card
Source: sample calculation
5
stages of the replacement plan
Source: sample plan

Five stages as the framework

The sample plan has five stages: inventory, a trial on one gate, the wave for employees, external companies and switching off the old format. A schedule for the shift planner means breaking these stages down into a calendar in which every stage has an owner, a gate and a shift.

The order matters. The inventory before the trial shows which readers support the new format. The trial on one gate reveals integration problems before they affect the whole workforce. External companies come after employees, because they have a different rhythm of entries and need separate communication.

Low-traffic windows

Issuing cards is a task for the gatehouse, so it is planned outside the peak of entries. In a three-shift plant the peak occurs at the start of each shift, and a low-traffic window usually falls in the middle of the shift. In the week before, measure the number of punches at the gate in 30-minute intervals and choose the intervals with the least traffic.

Assuming 5 minutes to issue and assign one card, one workstation issues 12 cards per hour. A wave of 100 people therefore takes about 8 hours of one workstation's work, or 4 hours for two. This arithmetic gives the number of workstations in the window, and from it the number of people in a wave.

Workstation hours per wave (example)

Workstation hours per wave (example)Bar chart: workstation hours for waves of 50, 100, 200 and 300 people0510152025hoursWave of 50 people: 4 hours4 hoursWave of 50 peopleWave of 100 people: 8 hours8 hoursWave of 100 peopleWave of 200 people: 17 hours17 hoursWave of 200 peopleExternal companies, 300 people: 25 hours25 hoursExternal companies,300 people
Source: Sample calculation: 5 minutes per card, values rounded to the hour

Waves by shift and gate

Divide employees by shift and by the gate they enter through, and assign an issue day to each group. An employee receives the new card when starting a shift, and from the first day after the issue uses only the new one. In this way, on each gate throughout the transition period the two formats mix, but no more than one wave at a time.

If the site chooses dual-frequency cards, which combine the 125 kHz and 13.56 MHz layouts, issuing does not have to be synchronised with the replacement of the readers at a given gate. With single-format cards, issuing at a gate must precede the switch of the reader, and the schedule shows this as a dependency.

External companies and visitors

External companies have a separate stage, because their shifts do not coincide with the site's shifts, and their cards are issued through a coordinator. Visitors do not have to receive physical cards: entry with a QR code from the invitation and registration at a kiosk limits the number of cards to be replaced.

Enter into the schedule the date from which the old cards of external companies stop working, and communicate it in advance. The details are in the checklists for external companies and for the switchover day of a wave.

Switching off the old format

The last stage is switching off the old format on the readers. 125 kHz cards transmit a fixed number without authentication, so copying them is cheap, and the transition period should therefore have an end date. The OSDP protocol with Secure Channel encrypts communication between the reader and the controller, unlike Wiegand, which sends data in clear text, so on this occasion it is worth asking the access control supplier whether the new readers can use it.

Switching off the old format is carried out outside the peak, ideally in a service window, and on the day of switching off the gatehouse has a pool of spare cards and a list of people who have not collected their new cards.

Checklist

Video

Frequently asked questions

Can card issuing be spread over several weeks?

Yes, and this is usually how it is done. The old format works until it is switched off, so the waves can last weeks, as long as the end date is set and known.

How do I set the number of issuing workstations?

Divide the number of people in the wave by 12 cards per hour and by the length of the window. A wave of 100 people in a 4-hour window needs two workstations.

What about employees on leave on the day of a wave?

Enter them on a separate collection list for when they return. The old format works until the switch-off day, so they do not lose access earlier.

Sources