Communication during a card replacement: employees and contractors

A queue at the gatehouse after a card replacement usually comes from communication, not from the technology. HR and safety can prevent it by informing employees and external contractors about the date, the pickup point and the emergency rules. Below are the practices for the rollout stage.

1,300
people covered by the replacement at the sample plant
Source: sample calculation

Why communication decides how the wave goes

With 1,000 employee cards and 300 external contractor cards (sample calculation), the replacement covers 1,300 people. If everyone comes on the first day, the gatehouse cannot issue that many cards in one shift. Spreading the work over time is therefore a communication task, not an equipment logistics task.

A well-planned message answers four questions: when, where, what to bring and what to do if the card does not work.

Message to own employees

HR knows the personnel numbers and the schedules, so HR sets the dates for departments or shifts. Safety adds the rules: the card is a condition of entry, and if it is missing the emergency procedure at the gatehouse applies.

The message contains the date for each group, the pickup point, the document needed at collection, and information that the old card works until a set date. It is worth repeating it in several channels, for example a notice board at the entrance, the intranet and a message to supervisors.

Sample distribution of cards issued in a wave week

Sample distribution of cards issued in a wave weekBar chart: 260 cards a day from Monday to Friday0100200300cardsMon: 260 cards260 cardsMonTue: 260 cards260 cardsTueWed: 260 cards260 cardsWedThu: 260 cards260 cardsThuFri: 260 cards260 cardsFri
Source: Sample calculation: 1,300 cards spread evenly over 5 working days

Message to external contractors

External contractors have different supervisors and different shifts, so the message goes through a separate channel: to the person who invites them and to the contract supervisor. For each contractor set a date and a contact person on the plant side.

If the plant has a multilingual workforce of contractors, the message and the safety induction video are prepared in language versions, and the assembly point is indicated separately for each group. This pattern is used at the packaging plant.

Guests: fewer cards to replace

Guests do not need physical cards: entry with a QR code from the invitation and registration at a kiosk limits the number of cards to replace. Phone registration, a health declaration at entry (a BRCGS requirement in food and packaging plants) and QR labels printed on demand support this model.

A QR code reader at the gatehouse costs around 1,000 PLN net per unit, outside the InnerWeb offer (indicative ranges from 2025-2026 deployments; individual quotation).

Emergency rules and finding the account

Describe what a person with a non-working card does: they report to the gatehouse, where security checks identity and lets them in under the emergency procedure. Punches from unknown cards go to the "card to be assigned" queue, so at the end of the day the administrator can see who tried to enter with an unassigned new card.

In the training module the account search by card requires at least 3 characters, returns at most 13 results and shows only active accounts with an assigned card, without revealing the card number. A training started from an account without a card goes to the account of the same person that has a card, so after a card replacement or addition no duplicate accounts are created.

Communication schedule

The timeline below is a planning assumption for the employee wave.

  • Two weeks before the wave: information about the date for the group
  • One week before: reminder with the pickup point
  • Day before: reminder to supervisors
  • Day of the wave: HR duty at the issue point
  • One week after the wave: list of people who have not collected a card

Checklist

Video

Frequently asked questions

How do you avoid a queue at the gatehouse?

By spreading the issue over group dates and days. With 1,300 cards in the sample calculation this gives 260 cards a day over five days.

Do guests receive new cards?

They do not have to. Entry with a QR code from the invitation and registration at a kiosk limit the number of cards.

What about people absent on their date?

They receive a backup date in the week after the wave, and their old card works until the set switch-off date.