What goes into the card and reader replacement budget
Replacing the card technology is not just buying media. Cards are the cheapest item on the list, and the largest share goes to readers and their installation, especially when there are many doors and some of them require work outside shift hours. The IT department should collect all the items before talking to purchasing, to avoid a second round of orders.
The budget items split into one-off and recurring. One-off items are cards, encoding, readers, installation and a contingency. Recurring items are replacement of lost cards, software updates and key reviews.
- Cards in a technology with authentication, for example DESFire EV3, with a reserve for new employees and lost cards.
- Card encoding: loading keys and applications, personalisation and, if needed, printing.
- Multi-technology readers, or readers compatible with the new card, in a number equal to the number of doors and gates.
- Installation and commissioning of the readers: electrician's work, configuration, passage test.
- A contingency for items not visible before the inventory, for example replacement of cables or the controller.
Sample calculation for a plant of 500 employees
The example assumes 500 employees and a card reserve of 12 percent, which gives 560 cards. There are 24 doors and gates with readers. These are example assumptions which do not describe any specific plant. The unit prices are also assumptions: a card at 15 PLN, encoding at 8 PLN per card, a multi-technology reader at 900 PLN, installation and commissioning at 250 PLN per reader, and a contingency of 10 percent.
The result: cards 8,400 PLN, encoding 4,480 PLN, readers 21,600 PLN, installation 6,000 PLN. The total before contingency is 40,480 PLN, the contingency is 4,048 PLN, and the grand total is 44,528 PLN. Readers and installation make up more than two thirds of the budget, so their number decides the cost.
Cost structure of card and reader replacement (PLN)
What changes the result most
The first factor is the number of doors with readers. A plant with 24 readers will pay for readers and installation about four times less than a plant with 100 readers, even though the number of cards is the same. That is why phasing the replacement by doors has the greatest budget effect.
The second factor is the condition of the readers. If the readers are already multi-technology and support DESFire after configuration, the budget shrinks to cards and encoding, which in the example comes to about 12,880 PLN plus the contingency. The IT department should establish this with the access control vendor before ordering the cards.
The third factor is the transition period. If old and new cards coexist for several months, readers supporting both technologies are needed. These are slightly more expensive than single-technology readers, but they save a double purchase.
Division of costs between IT, purchasing and security
In practice three departments share the budget. IT is responsible for the technical specification, the keys and the integration with the access control system. Purchasing handles offers and delivery dates. Security chooses the doors and the schedule for issuing cards. It is good to assign the budget to one owner, so that the items do not scatter across different cost centres.
If the replacement is part of a wider project, for example a migration to OSDP, part of the cost of readers and installation falls to that project, and the card replacement adds mainly cards and encoding.
What this budget does not cover
The budget does not include the costs of the permit and training system. InnerWeb does not manufacture or replace readers and access control cards, and it integrates with the client's existing access control system. Replacing the card technology on the access control side does not require a change in permission logic, so there is no separate card replacement item on the side of the training and permit system.
The price of an InnerWeb integration is individual. The other amounts in this calculation are example assumptions, not an offer; the real budget is set on the basis of the access control vendor's offers and a survey of the doors.
Sample calculation: card and reader replacement, 500 employees
| Parameter | Value |
|---|---|
| Number of employees | 500 people |
| Number of cards with a 12% reserve | 560 cards |
| Card price | 15 PLN per card |
| Card encoding | 8 PLN per card |
| Number of readers | 24 pcs |
| Price of a multi-technology reader | 900 PLN per unit |
| Installation and commissioning | 250 PLN per reader |
| Contingency | 10 % of total |
Result: Cards 8,400 PLN + encoding 4,480 PLN + readers 21,600 PLN + installation 6,000 PLN = 40,480 PLN; contingency 4,048 PLN; total 44,528 PLN.
Note: Sample calculation on assumptions, not an offer. The plant replaces the unit prices with its own offers from the access control vendor; the price of an InnerWeb integration is individual.
Video
Frequently asked questions
Do all the readers have to be replaced?
Not always. If the readers support the new card technology after configuration, a change of cards and encoding is enough. The IT department should confirm the reader model with the access control vendor before ordering.
Can the replacement be spread over phases?
Yes, and it is usually cost-effective. It starts with the doors of highest importance, and the transition period requires readers that support both card technologies.
Does replacing the cards increase the cost of the permit and training system?
No. The permit system accepts events from the access control system, so changing the card technology on the access control side does not require a change in permission logic.
Where do we get reliable prices for the budget?
From the access control vendor's offers and a survey of the plant's doors. The amounts in the calculation on this page serve as a template and show the proportions of the items, not market prices.