The rule: payment follows a working function
The purchasing department has one task with instalments: a payment must not run ahead of a working function. If an instalment is tied to a calendar date, the buyer pays even when the stage is late. If it is tied to stage acceptance, the supplier is motivated to close the stage, and the buyer pays for the result.
The words stage acceptance alone are not enough. What is needed is a criterion that can be checked without interpretation: the function works or it does not. Below we describe how to formulate such criteria, using examples from implementation offers.
Three instalments and three acceptances: a template
An implementation of a system for a logistics centre at 34,000 PLN net in 7 items was paid in 3 instalments tied to stages: one third at the order, one third after stage I, one third after go-live. The three-stage variant has an acceptance after each stage.
The acceptance criteria in this template are concrete. Stage I is a working training module and an instance with the map. Stage II is an accepted test permit. Stage III is the production go-live. Each of these can be shown on the screen of the acceptance committee and described in one sentence of the protocol.
- stage I: a working training module and an instance with the map
- stage II: an accepted test permit
- stage III: production go-live
Items of the work permit pilot (18,000 PLN net)
Amount examples: 18,000 PLN and 42,000 PLN
A pilot of work permits is an implementation of 18,000 PLN net in 7 items, paid in 3 instalments of 6,000 PLN. The items are analysis 2,400, server 3,600, procedure 4,200, cards 2,400, hazards 1,600, contractors 1,800 and tests 2,000 PLN net. The sum of the items is 18,000 PLN.
An implementation of a system for external contractors at 42,000 PLN net, also in 7 items, was paid in three equal parts of 14,000 PLN: at the order, after stage I and after stage II, with go-live in about two months. Note that in this template the third instalment falls on the moment of go-live, not at the end of a calendar month.
The two-stage variant and when to choose it
A schedule in two stages with 50% paid at the order and 50% after go-live ends with the acceptance and the production go-live at the end of month 2. It is simpler: fewer protocols, fewer meetings, one acceptance decision. It does, however, mean a larger payment up front, so for large amounts the purchasing department may prefer three instalments.
A practical rule: the less the buyer knows the supplier or the technology, the more acceptances are worth writing down. With a known supplier and a short implementation, the two-stage variant may be enough.
Share of payments at each moment: two and three stages
- Two stages
- Three stages
Acceptance, remarks and settlement: clauses for the contract
Put four elements into the contract. First, the acceptance criterion in the form of a verifiable test. Second, the person on the buyer's side who signs the protocol. Third, the deadline for acceptance counted from the notice of readiness, so that the buyer does not drag it out. Fourth, the rule for remarks: non-critical remarks do not block an instalment, but they have a deadline for removal.
Also record what happens in case of delay. After go-live, the SLA parameters apply. The SLA parameters (availability, response and repair times) are set in the maintenance contract, for example 99.5% availability in a month. Add 23% VAT to the net amounts, and the price ranges are indicative and require an individual quotation.
Checklist
Video
Frequently asked questions
Do the instalments have to be equal?
No. The offer examples use equal parts (6,000 and 14,000 PLN net), but the split is set individually.
Who confirms the stage acceptance?
The person named in the contract on the buyer's side, ideally the one responsible for the given area, for example the HSE manager for the training module.
Does the contract provide for contractual penalties?
Liability and settlement matters are set individually in the contract. The SLA parameters (availability, response and repair times) are set in the maintenance contract, for example 99.5% availability in a month.