Structure of the migration budget
There are four cost items. The first is readers supporting OSDP version 2 with Secure Channel. The second is labour: dismantling, installation, address configuration and enabling encryption. The third is controllers or interfaces, if the existing controller does not support OSDP. The fourth is cards, when the card technology is changed at the same time.
The amounts below are indicative ranges from 2025-2026 deployments; each quotation is priced individually. They serve to plan the budget and are not an offer.
Cabling item: where the savings are
On one RS-485 OSDP bus, several readers can operate in a chain, while Wiegand needs a separate bundle of wires for each reader. During the migration of an existing installation, cables already laid can often be reused, which limits the cost of new routes to places where the cable is damaged or too long.
The permissible OSDP cable length is in the range of several hundred metres, and for Wiegand about 150 m. The values depend on the cabling and must be confirmed in the manufacturer's specification. The saving comes from fewer wires and routes at new doors, not from a free migration of the old ones.
Ranges of the 20-door budget items (PLN)
- Lower bound
- Upper bound
Controllers: the largest unknown
Whether the existing controller supports OSDP is decided by the controller documentation and the access control supplier. If it does, the controller item is zero. If not, the budget includes an interface or a controller replacement, and this item most often decides the upper end of the range.
That is why the first cost step is an inventory: the controller model, the firmware version and the number of reader inputs. Only from this does it follow whether the budget sits in the lower or the upper part of the range.
Cards: a cost separate from the protocol
Moving from Wiegand to OSDP alone does not secure the card: if the card is 125 kHz or another unprotected technology, it can be cloned in front of the reader. Replacing the cards is therefore a separate budget item and a separate decision, which is worth taking together with the choice of readers so that the readers are not bought twice.
We compare the cost of the cloning risk with the cost of replacing cards in a separate material on cloning the 125 kHz card.
What the migration budget does not include on the InnerWeb side
InnerWeb does not produce or replace readers, so the migration of a reader generates no costs on the InnerWeb side. The swipe event integration keeps working, as long as the access control system keeps sending events, and a change of the reader-to-controller protocol requires no changes on the InnerWeb side.
Sample calculation: migration of 20 doors
| Parameter | Value |
|---|---|
| OSDP v2 readers with Secure Channel | 800-1,500 PLN per unit (20 units) |
| Labour per door | 300-600 PLN per door |
| Controllers or interfaces | 0-20,000 PLN in total |
| DESFire cards, 400 pcs | 8-15 PLN per card |
Result: Total from PLN 25,200 (controller supports OSDP, lower prices) to PLN 68,000 (interfaces, upper prices).
Note: Sample calculation. Indicative ranges from 2025-2026 deployments; each quotation is priced individually.
Video
Frequently asked questions
How much does the move to OSDP cost for 20 doors?
In the sample calculation, from about PLN 25,200 to PLN 68,000, depending on whether the controller supports OSDP. These are indicative ranges from 2025-2026 deployments; each quotation is priced individually.
Can the old cables be reused?
Often yes, if they are in good condition and within the permissible length. The specification of the reader and controller manufacturer confirms the values.
Is replacing the cards necessary?
Not for the protocol alone, but a 125 kHz card remains open to cloning, so replacing it is a separate decision.
Does InnerWeb add costs?
No. Moving the reader-to-controller protocol requires no changes on the InnerWeb side.