Implementation costs through a partner: example calculation

The customer's implementation budget through a partner consists of several items of different nature: the subscription for licences, the one-off implementation cost, subscription options, training and the partner markup. We show a calculation for a project with 50 licences, with explicit assumptions, so the partner and the customer can recalculate it with their own data.

68,560 PLN
example first-year budget, net
Source: example calculation
18 days
partner's own work in the example
Source: example calculation
42,240 PLN
example cost of the following year, net
Source: example calculation

Items of the implementation budget

The first-year budget has five items. The first is licences, that is the subscription for active users. The second is the one-off implementation cost covering installation, configuration and acceptance. The third is subscription options, for example BLE transmitters. The fourth is training. The fifth is the partner markup on the items the partner invoices.

Producer prices are prices without the integrator markup, so every markup sits on the partner's side and should be visible in its offer. The amounts below are indicative ranges from 2025-2026 implementations; individual pricing applies.

Producer price components

The fixed 50-licence package costs 2,500 PLN net per month, that is 30,000 PLN per year. The flexible variant for the same number of users is 80 PLN times 50, that is 4,000 PLN per month, so for a stable group the package is cheaper by 1,500 PLN per month.

A typical implementation costs from 12,600 to 34,000 PLN net one-off. BLE transmitters cost 700 PLN net per month per 100 pieces, and the training module 1,200 PLN for the first site and 600 PLN for each additional one. The choice of options depends on scope, not on the number of licences.

Structure of the first-year budget, 50 licences

Structure of the first-year budget, 50 licencesHorizontal bar chart: licences 30,000, implementation 25,000, transmitters 8,400, markup 3,960, training 1,200 PLN010,00020,00030,000PLN netLicences (50 package)Licences (50 package): 30,000 PLN net30,000One-off implementationOne-off implementation: 25,000 PLN net25,000BLE transmitters (100 pcs)BLE transmitters (100 pcs): 8400 PLN net8400Partner markup 10%Partner markup 10%: 3960 PLN net3960Training (1 site)Training (1 site): 1200 PLN net1200
Source: Example calculation based on the assumptions in the Calculation section

The partner's own work

Beyond the costs in the price list, the partner bears the cost of its own work: preparing the offer, site surveys, configuration of roles and the permissions matrix, integrations with customer systems, training of administrators, acceptance and support after launch. The calculation assumes 18 working days for a project with 50 licences, spread over 3 months.

This assumption is an example, not a norm. A project without integration with an access control system will be shorter, and one with integration of card-reader events and several halls will be longer. The partner should record its own assumption before pricing, and after the first project correct it with data from actual work time.

Where the partner's time is most often lost

Most time is consumed by agreements on the customer side: network access, naming the process owners, collecting the list of administrators and dates at the plant. It is worth including them in a checklist before the visit and invoicing them as a separate stage.

Result: first-year budget

The calculation assumes an implementation at 25,000 PLN, the fixed 50-licence package, 100 BLE transmitters on subscription, the training module for one site and a partner markup of 10% on subscription items. The sum of the producer items is 64,600 PLN net, and the partner markup adds 3,960 PLN.

In total the customer pays about 68,560 PLN net in the first year. In later years the implementation and training cost disappears, so the annual subscription cost including markup is about 42,240 PLN net.

How to recalculate for your own project

Start with the number of active users, because guests and drivers are not counted. Then select the package, check the number of transmitters based on floor area and route length, choose the options, and only then add the markup and your own work.

A cautious rule for the partner: a calculation shown to the customer should have two separate columns, the producer price and the partner part. This makes purchasing easier for the customer and protects the partner from questions about its margin structure.

Example calculation

First-year budget for 50 licences

Assumptions
ParameterValue
Fixed package, 50 licences2500 PLN net/month
One-off implementation (within the 12,600-34,000 PLN range)25000 PLN net
BLE transmitters100 pcs at 700 PLN net/month per 100 pcs
Training module, first site1200 PLN net
Partner markup on subscription items10 %
Partner's own work18 working days

Result: Licences 30,000 PLN + implementation 25,000 PLN + transmitters 8,400 PLN + training 1,200 PLN = 64,600 PLN; markup 10% on licences and transmitters (38,400 PLN) = 3,840 PLN, and on training 120 PLN, total 3,960 PLN. Sum: 68,560 PLN net in the first year.

Note: Example calculation based on the assumptions above. Indicative ranges from 2025-2026 implementations; individual pricing applies.

Video

Frequently asked questions

Does the partner markup apply to the implementation?

In the example the markup applies to subscription items and training, while the implementation price is the partner's price. A partner may adopt a different model, but must describe it in its offer.

What does the second year cost?

In the example about 42,240 PLN net: licences, transmitters and markup, without implementation and training.

Are 18 days of work a binding value?

No. It is an example assumption for a project without complex integrations. The partner should replace it with its own estimate and correct it after the first project.

Let's recalculate your project

Give us the number of users and the scope. We will prepare a calculation with the producer price and the partner part shown separately.