Place of the stage in the schedule
In a 6-8 week schedule, training materials (video and PDF in 2 languages, with tests) are created in weeks 3-4. Before that the plant delivers the list of companies, materials, permit templates and the plant layout. Later the team training and the launch take place.
For the project manager this means that weeks 3-4 have a hard entry point: without materials from the plant there is nothing to turn into training. A delay in delivery shifts the whole stage.
What the plant must deliver before week 3
The condition for success on the plant's side: at least 2 administrators and timely delivery of the list of companies, training materials, permit templates and the plant layout. We recommend confirming this in writing at the end of week 2.
Training materials in the plant often exist only as presentations and workstation instructions. It is worth collecting them, assessing whether they are up to date, and naming a subject owner for each material who will approve the test questions.
Order of work in weeks 3-4
Week three: preparing video and PDF in two languages, a draft of test questions, approval by the subject owners. Week four: loading the materials into the system, setting up the tests, assigning them to training types and a trial run on the test account.
The kiosk training system walks the participant through the material (PDF slides or video) and a multiple-choice test. We do not promise trainings in every language, because they depend on the plant's materials. Two languages from the plan are therefore the realistic scope, and each additional language requires separate material.
Adding a video to the library is a data change in the installation's catalog, so corrections in week four do not require releasing new code.
Stage acceptance
Acceptance is a passed test training and a test permit with a PDF printout. The test training is taken by the person designated by the plant on the test account, from material to test result. The test permit shows that the path from training to work functions.
It is worth reducing the acceptance protocol to a few yes or no questions: the video in two languages plays, the test works, the result is saved in the record, the PDF printout is legible. Every no has an owner and a date for the fix.
Pitfalls of the schedule
The most common pitfall is waiting with the materials until week three. The second is having too many people approve test questions, which lengthens the cycle. The third is the lack of a deputy when the only subject owner is on leave.
We recommend a contingency plan: if a material is not ready, the training stays in its basic version, and the extended version comes after acceptance as an additional training. Launching another module requires training of the implementation team and configuration to the plant's process.
Video
Frequently asked questions
What if the materials are a week late?
The stage acceptance shifts. Set a contingency plan with a basic version of the training.
How many languages does the plan cover?
Two languages with tests; additional ones require separate materials.
Who passes the test training?
The person designated by the plant, on the test account.
Can materials be added after acceptance?
Yes. Adding a video to the library is a data change in the catalog, not a code change.
Rollout and training schedule
We will arrange weeks 3-4 around your plant's materials. Book a talk.