Two models: where the training time is spent
In the first model the person completes the induction training at home, before leaving, and arrives at the plant with a valid result. In the second model they do it after arrival, at a workstation in the plant. Attendance at a workstation training is recorded in the system and can feed the list of people present, so the second model is fully supported.
The training time itself is similar in both models. What differs is the time lost: the second model adds the queue for the workstation and the downtime of a crew waiting to finish the training of the last person.
Calculation for 60 people
Assumptions: 60 contractor employees, 25 minutes of training per person, labour cost of 120 PLN per hour, one workstation at the plant, about 10 minutes of waiting per person at the kiosk model, and 3 minutes of verification at the gate in the model before arrival.
At the kiosk: training time 60 times 25 minutes is 25 hours, which is 3,000 PLN, plus waiting 60 times 10 minutes, which is 10 hours and 1,200 PLN. Total 4,200 PLN. Before arrival: the same 3,000 PLN plus verification of 3 hours, which is 360 PLN. Total 3,360 PLN. The difference is 840 PLN, about 14 PLN per person.
What the numbers show
The cost difference is moderate. The deciding factor is something else: the training station is occupied for 25 hours in the kiosk model, against only 3 hours in the pre-arrival model.
What the calculation does not cover
It does not cover the cost of delaying the start of works or the time of the supervisor. During a shutdown with a tight schedule these items often matter more than the hourly rates themselves.
Cost of training 60 people: at the kiosk versus before arrival
The kiosk as a bottleneck
One workstation serving 60 people at 25 minutes each means more than 3 working days of 8-hour shifts. For single visits this is not a problem, but during a maintenance shutdown registering a thousand people in a few days will not work on a single kiosk.
Hence the recommendation: pre-arrival induction training for groups, the kiosk for single visits and for top-ups. The kiosk then keeps its role as verification and brief confirmation, not as a mass training room.
When training at the kiosk makes sense
The kiosk model wins when visits are short, one-off and unannounced: a courier, a service engineer called out for a fault, a guest. In such cases training before arrival makes no sense, because the person does not know a day in advance that they will come.
It also wins where the contractor has no access to the internet or to a device for training. There the kiosk removes the need for preparation and does not require paying for the time before departure.
How to prepare for the switch to pre-arrival training
Invite the company in advance: the system handles visits planned with an earlier invitation and mass invitations for guests. The invitation should state the validity date of the training and a link. The external companies module shows who in the company has already completed the training, so the coordinator does not have to ask each person separately.
Keep the kiosk as the fallback path. A person who forgot about the training will complete it at the workstation, and their attendance will be visible on the evacuation list as training in progress.
Sample calculation: 60 contractors
| Parameter | Value |
|---|---|
| Number of people | 60 people |
| Training time | 25 min per person |
| Hourly cost | 120 PLN |
| Waiting at the kiosk | 10 min per person |
| Verification at the gate | 3 min per person |
Result: At the kiosk 4,200 PLN, before arrival 3,360 PLN, difference 840 PLN.
Note: Sample calculation; rates and times are assumptions, not data from a plant.
Video
Frequently asked questions
Does training before arrival always have to be accepted?
No. The plant may require a brief confirmation at the gate. The kiosk is then a verification step, not a training room.
Is attendance at the kiosk visible on the evacuation list?
Yes, attendance at a workstation training is recorded and can feed the list of people present.
For whom is the kiosk the best path?
For short, unannounced visits: a service engineer called out for a fault, a courier, a guest.
How do I calculate the cost at my plant?
Use your own number of people, training time and hourly rate. The calculation on this page is a sample.