What the demo cost is made of
The demo costs people's time, not licences. It runs on a separate demo instance with its own area, locations and transmitters marked with an external identifier, so it does not touch the plant's production systems. The cost splits into five items: hall data, accounts and templates, server and database copy, trial run of the scenario, and a reserve for corrections.
The figures below are a sample calculation based on the assumptions described further down, not a measurement from a specific plant. The quality of each plant's plans differs, so the time needed for data can vary by several dozen percent.
Hall data: the largest item
The plant data for the demo is the hall georeferencing (a reference point and the rotation of the plan relative to north), building shapes and locations with transmitter numbers. If the plant has a plan in vector format, the work goes quickly. A scanned drawing requires tracing the building shapes by hand and a longer fit to the map.
Accounts, templates and risks
Demo accounts use addresses in a domain reserved for testing, so there is no risk of a notification reaching a real person. The account password is kept as a CI/CD variable, not in the repository. Permit templates, including ALARM and SOS, must be attached to the hall location, otherwise the alarm will not appear on the map. Risks are assigned to locations, so a permit in a given hall immediately shows the risks of that place.
Server, database copy and trial run
Before any data change on the demo instance, a database copy is made (a gzip-compressed dump) and its size is checked. The demo is started and stopped with a start/stop command from a single script, and its state is checked with a status command. A full dress rehearsal, including the siren and visitor registration, is the last cost item.
What the plant has to provide
The plant contributes little. It needs a hall plan, the locations where alarms should appear, agreement on the visitor registration scene, and a person who will learn the scenario. For the board, time also matters: the demo itself usually lasts a dozen or so minutes, but a meeting with discussion takes an hour.
Plan the equipment as well: a computer with sound and a large screen, network access and a spare device. The demo server is sized with a margin of resources and checked before the demo, because a failure during a presentation to the board is the worst outcome. It is a small cost that prevents that failure.
Breakdown of working days for demo preparation
When the demo pays off
The demo pays off when it filters out functions that do not fit before a paid pilot. If the board sees the map, alarms and the visitor path on its own data, the decision on pilot scope is made faster, and the pilot itself can be narrower. The purchasing department's comparison is described on a separate page about demo savings versus a pilot.
The second return is less visible: the demo exposes gaps in the plant's data, such as an outdated hall plan or no owner for the risks. It is better to find them during the demo than in the first week of the pilot.
The last item in the calculation is the cost of not running a demo. A board that has not seen the system often asks for an extra meeting, extra materials or a broader pilot just in case. Each of these uses up time on both sides. A demo on the plant's own data replaces them with one meeting and one concrete demonstration.
What the demo does not cost or replace
The demo does not require installing transmitters or changing the access control system. It also does not replace a pilot: it shows how the system works on real data, but without real traffic of people and vehicles. InnerWeb is an independent system that complements the client's existing systems (access control, time attendance, HR, ERP), and location works without GPS, using signals from several transmitters averaged on the map. The pilot decides this, not the demo.
The company figures that may be quoted during the demo: 20 deployments and pilots, and a 100% conversion rate from pilot to deployment.
Sample calculation: working days to prepare the demo
| Parameter | Value |
|---|---|
| Hall data (georeferencing, building shapes, locations) | 2 days |
| Demo accounts and permit templates | 1 day |
| Server and database copy | 0.5 day |
| Scenario trial run (SOS, stillness, visitor) | 1 day |
| Reserve for corrections | 0.5 day |
Result: Total 5 working days, assuming the plant provides a hall plan in a form that can be traced.
Note: Sample calculation based on the assumptions above; it is not a price quote. Individual pricing follows an analysis of the plant's plans.
Video
Frequently asked questions
Is the preparation chargeable?
Scope and terms are agreed individually. The calculation on this page shows the structure of the effort, not a price list.
What determines the preparation time?
Above all, the quality of the hall plan. A vector plan shortens the work, a scanned drawing lengthens it.
How long does the demo itself last?
The scenario takes a dozen or so minutes. The rest of the meeting is discussion and writing down the conclusions.
Does anything need to be dismantled at the plant after the demo?
No, because the demo requires no installation. After the meeting the instance is stopped and the demo account markers are cleared.