Why acceptance is a separate step
A service company that has finished its work considers the task done. The plant has its own criteria: whether the scope matches the order, whether the equipment is in the state it was before the visit, whether doors and cabinets have been closed and access withdrawn. Acceptance separates these two perspectives and records who confirmed that the work had ended.
The electronic work permit defines the task, the place and the time window of the contractor's work and passes through the preparation, main work and closing phases. Acceptance is the natural moment of moving to the closing phase: until the permit is closed, the work is formally still in progress.
Part 1: scope and time
The first question for the person accepting the work is whether what was in the permit has been done, within the time window the permit set. Compare the scope with the description of the task, and the time of exit with the end of the window. An exit after the window requires a comment, because it stays in the register as an exception.
The flow of permits issued to an external company lets the issuer on the plant side and the contractor work on the same permit, and the assigned work is visible on the company's screen. As a result the person accepting sees what the contractor reported, without collecting information from e-mails.
Entries to the example server room requiring acceptance
Part 2: the state of the server room and the cabinet
The second part is a walk around the workplace. Check whether the cabling, labels and cabinets are in the state they were before the visit or as ordered, whether no tools, data carriers or packaging have been left behind, and whether the doors of the OT cabinet are closed. For cabinets on the shop floor add a check of the surroundings: the service may have removed a cover or moved equipment nearby.
If the scope included a change of configuration, the person accepting confirms its description and date. Here the role of the list ends: the technical assessment of the change belongs to IT or automation specialists, and the list ensures that the assessment was made and recorded.
Part 3: exit and the register
The third part concerns the trail. Every scan at the security screen is an audit act and is written to the entry and exit register, so check whether the register contains both the entry and the exit of the service technician. A missing exit in the register means that the person may have left the place by another route or that the entry was not saved. Both situations require an explanation before the permit is closed.
If the door is served by the client's access control system, card read events reach InnerWeb through a webhook and are linked with permits and attendance. InnerWeb does not manufacture or replace readers.
Part 4: withdrawing access
The fourth part is the withdrawal of permissions. A planned visit replaces the one-day permit requirement at the gate, so after the day of the visit entry is no longer possible without a new visit or permit. For a multi-section permit the person accepting checks whether closing it really ends access. Trainings, qualifications and an active account of the technician still decide on entry at the next visit.
Record in the closing comment whether the contractor has a planned next visit. The visit supervisor may be the same person, but the system calls the supervisor once, at the first entry, so subsequent visits require a separate arrangement.
Part 5: evidence and report
The last part is the evidence of acceptance. A closed permit with the time and author of the closing, together with the entry and exit register, forms a complete set. Changes of permits are saved together with the author and the time. Periodic reports, sent daily, weekly or monthly, with tables and a PDF attachment, let you review all acceptances in a period without submitting them by hand. With 288 entries a year in an example server room served by four companies, such a review is the only practical way of control.
Checklist
Video
Frequently asked questions
Who should accept the service work?
An IT employee or automation engineer responsible for the place, preferably someone other than the person who issued the permit. The role of the person accepting should be recorded in the access policy.
What to do when the register has no exit of the technician?
Do not close the permit. Establish the route of exit and the reason for the missing entry, and record the result in a comment. A missing exit can also be the effect of a reading problem.
Does acceptance replace the technical assessment?
No. The list ensures that the assessment was made and recorded. The substantive assessment is made by an IT or automation specialist.
Organize the acceptance of service work
We will show how closing the permit, the entry and exit register and withdrawing access form one acceptance evidence set. Arrange a conversation with the InnerWeb team.