Why check after a shutdown
A kiln shutdown changes the plant: new locations appear, some points disappear and lines get different fields. Risks are assigned to locations, so a change in the structure also changes which hazards the system shows at the permit.
In an analysis of 106 permits collected over 9 weeks at a continuously running plant, 76 concerned two halls, and 43 concerned hot work and 40 work at height. These halls and types of work need checking first.
Location and risks: five checks
The first group of checks concerns whether the risk is in the right place. Check whether the risk is assigned to a point at the machine, not only to the whole line. The contractor should choose a specific point, so the risk must also apply to a specific point.
The second check is the general location. In the analysis, 44 of 106 permits pointed to the building, Other or Whole line. For the kiln, check whether the risks for such locations cover the worst case.
Lines that do not overlap
A line without its own shape does not inherit the outline of the whole building, but gets a separate field. After a shutdown, check that no two lines lie on top of each other, because the risks of one would then appear at the other.
Machine position within the line field
A line with a machine marker passes into the building zone in which the marker physically lies. A stack of at least three lines at one point is not a position. The first location of the line stands at the machine point.
Permits in the analysis by type of work
Permits and watch: five checks
The second group concerns the process. A permit for especially hazardous work is approved or rejected only by the user on the plant side, so before restarting check who holds the approver rights and whether the duty in the 6:00 to 10:00 window is staffed.
Hot work must pass monitoring at 1 h and 4 h, and closing is blocked until at least 3 hours have passed. Check whether open tasks from the shutdown have been moved to the main works, because unclosed tasks do not block the permit from moving between phases.
How to use the checklist
Go through it on the same day the plant returns to operation, and record the result. Settle the points that did not pass before the first permits are issued to contractors. The record of the check is audit proof that the plant verified the risks after the change in structure, but it does not replace the plant's own procedure.
Checklist
Video
Frequently asked questions
Does the checklist need repeating after every shutdown?
Yes, after every change of the location structure, because risks are assigned to locations. For small changes a shortened version for the changed lines is enough.
Who should fill it in?
The safety manager together with the maintenance department. Acceptance of permits stays with the users on the plant side.
What if the lines of a location overlap?
Correct the division of the line field before permits are issued. A line without its own shape should get a separate field, so that risks do not mix between lines.
Does the checklist also apply to external companies?
Indirectly. The contractor chooses the point at the machine and keeps the watch after hot work, and the plant-side risk check makes sure that this point has the right hazards.