Starting point: work orders circulating on paper
In a power facility a work order is not a formality but the document that decides whether a team steps onto equipment that is de-energised. The order and the switching and safeguarding card circulated between the issuer, approving parties, the person granting access and the team. Each handover meant another signature on a sheet, and the actions reached the system only after a return to the office.
The result was double data entry and discrepancies between paper and the register. With several jobs running on one circuit, the person withdrawing a safeguard could not be sure that nobody else was still working on it. Contractors learned about hazards from an oral briefing. Pauses and restarts were lost between shifts, and after an event the evidence had to be assembled from scattered documents.
- The current state of the order is known only to the person holding the sheet.
- Field actions are entered into the system after the return, with delay and transcription errors.
- No view of other active jobs on the same circuit.
- Pauses and restarts between shifts are not documented.
Questions the plant asked
Before the pilot decision, the site's departments formulated three questions. Will the system reproduce the current PnP and KPZ procedure without changing the instructions? How does the system block access for the team until the last safeguard on the card is confirmed? Does the external contractor see only its own orders, and must it install an app?
These questions describe well what working with orders in the power sector is about. It is not a new form but a hard link between the sequence of actions and the ability to grant access to work. That is why the solution was designed around the site's procedure and not around a generic template.
How access works: paper versus digital flow
- Paper
- Digital flow
Solution: the same procedure, a different medium
The system reproduces the current PnP and KPZ procedure one to one, based on the site's own forms: the medium changes, the instruction does not. An order passes through three phases: preparation, main work and closure. Each phase is a list of tasks assigned to roles from the plant's procedure, and a task that requires a signature can be closed only by an authorised person. The procedure, phases, roles, approvals and print templates are set up in workshops based on the current forms.
The switching card as preparation tasks
KPZ items such as switching, disconnection, protection against re-energising, earthing, marking and verifying absence of voltage are preparation tasks with a sequence, a responsible person and a signature. Until the last safeguard is confirmed, access stays blocked, and the contractor sees a waiting status instead of consent to work.
In the pilot, the KPZ is a configuration of the order engine, not a separate module. Site-specific elements that configuration cannot cover are priced separately as an extension before implementation.
Suspension, restart and closure
Suspending work does not remove safeguards. An additional disconnection during the work is a new task that conditions the restart. Closure requires confirming that the zone has been cleared and that safeguards have been withdrawn in the reverse order to that in which they were applied. The system records every action with its author and time, without copying from paper.
Coordinating work on one circuit
The most dangerous situation in a facility with many parallel jobs is a safeguard withdrawn by a person who does not know that someone is still working on the circuit. Orders are assigned to locations from the facility tree: building, floor, device. When an order is issued, the system shows other active orders in the same location, and the work map shows active orders, their phase, hazards and protective measures.
The sequence and roles of safeguards follow the card templates and the safe-work organisation instructions for power equipment in force at the site. They are configured in a workshop in line with those documents and not imposed from outside. The same process diagram is attached to the PnP and KPZ as a file available on a tablet in the work zone.
Scope of the pilot
External companies and a tablet in the field
An external contractor works in a browser and sees only the orders assigned to its company. It does not have to install an app, and external companies and guests are not counted as workstations in the fees. In the work zone an offline queue is available on the tablet, which matters where network coverage is limited.
Closing the main work requires an answer to an additional control question, and tasks with a signature can be closed only by authorised persons. This limits the risk of mechanically clicking through tasks without checking the state of the equipment.
Result and scale of the pilot
The pilot covered one facility on a separate server, about 50 workstations on the plant side and a period of 3–6 months. Pilot implementation fell within a range of roughly a dozen thousand zloty net, and the fee for external companies and guests was zero (indicative ranges from 2025–2026 implementations; individual quotation). In the long run the process pattern is meant to become a group standard with local specifics: the location tree, role holders and form templates.
For an NIS2 essential entity this matters beyond health and safety. A single record path with author and time makes it easier to show that operational processes around equipment are supervised, and it provides evidence for an audit. The system supports meeting the requirement but does not replace the compliance assessment on the entity's side.
Conclusions for other CHP plants
First, start with a pilot in one facility, then copy the process template to the next ones. Second, do not change the departments' instructions: reproduce the forms 1:1 and change only the medium. Third, link the PnP, the KPZ and the contractor in one process, so that the system does not let an order move to the next phase until the blocking actions are confirmed.
Video
Frequently asked questions
Does the system change the safe-work organisation instruction?
No. The PnP and KPZ forms are reproduced one to one. The medium changes, while the sequence and roles follow the templates in force at the site, set up in a workshop.
What happens to safeguards when work is suspended?
Suspension does not remove safeguards. A change to the circuit during the work is a new task that conditions the restart.
Must an external company install an app?
No. The contractor works in a browser and sees only the orders assigned to its company. External companies and guests are not counted as workstations.
Is the KPZ a separate module?
In the pilot the KPZ is a configuration of the order engine: preparation tasks with a sequence, a responsible person and a signature. Elements that configuration does not cover are priced separately as an extension.